BASIC DIFFRANCE BETWEEN LIMIT STATE METHOD AND WORKING
STRESS METHOD?
Answer / mizpah
Working stress method of design based on the elastic theory in which materials, concrete and steel are assumed to be stressed well below their elastic limit under the design loads. Working stressess (permissible stress) for the materials are determined by dividing the ultimate or yield stressess by suitable factor of safety values.
Limit state method of design based on limit state concept, te structure shall be designed to withstand safely all loads liable to act on it throughout its life;It shall also satisfy the serviceability requirements, such as limitations on deflection and cracking. The acceptable limit for the safety and serviceability requirements before failure occurs is called a "limit state". The aim of design is to achieve acceptable probabilities that the structure will not become unfit for the use for which is intended, that is that it will not reach a limit state...
| Is This Answer Correct ? | 9 Yes | 3 No |
which grade of steel is better for construction of building under earthquake zones ? why?
3. What are the disadvantages of your present job, things you do not like about it?
if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?
can we use .5 water-cement ratio for any type of cement?
How we can calculate cement and sand for a wall 25ft x 28ft.Thickness of wall is 9inches.
what is a moment connection and shear connection ? where it provided ? why it provided ?
The company is following same question pattern and giving same questions in all year for all batches from the starting of company they didnt even able to frame new question,,so guys if u want to place in cccl just mail me i will send the questions....ramyakvb@gmail.com....if u mug all those answers u will be selected no proper selction procedure is considered so it is better to place in some other company...All The best dont attend cccl
Outline ten different ways in which typical bill of quantities can be used?
how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this quantity can be calculated?
in the earthquqke the profile of water on dam is parabolic or not
what are the minimum compressive strength required for the concrete cube for different grades & different days .Please give me an answer.
How much will be Concrete required for one Sq.meter of area for building work?
2 Answers PSD, SMC, Tudor Infrastructures,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)