what is meaning of sympathetic tripping with respect to
relays and give the values for current carrying capacities
for copper and aluminium cables from 16sq mm to 500sq mm
Answer / jaimini soni
Sympathetic trips are undesirable relay operations for
unbalanced- or high-load conditions which
occur during or immediately following out-of-section
faults. The root cause of the sympathetic
trip problem is the type and connection of loads served by
distribution feeders. There are two
classifications of sympathetic trips: those which occur due
to delayed voltage recovery
conditions, and those which occur due to the load unbalance
during an out-of-section fault.
| Is This Answer Correct ? | 2 Yes | 0 No |
what r the main parts of central chiller plant in Air conditioner ? explain the function of each?
what is the first step of dg shycroning ?
Why do we use only Sinusoidal Wave in AC supply why not the Square,Triangle or Sawtooth etc?
1.In two wattmeter method if one wattmeter shows Negative reading then wat is reason? 2.Wat is the reason for low voltage in houses? 3.Wat is meant by current and voltage? wat is difference between the two?
When and where resistance earthing is used ? How to calculate the time constant for earth fault
As per is what is distance between two chemical type earth pit
when we increased the current what do ?
how dc load convert to ac load
how many types of ACB breakers, describe briefly..?
How can Inductive load reduce the line voltage of HV transmission line and vice versa Capacitive load?
A commercial Building is designed with 14th floor levels with indoor substation of three phase transformer with rated capacity of 1000 Kva.The transformer delivered 65% of its rated capacity at 0.67 power factor lagging.Because of low power factor, the power customer was penalized and certain cost was charged accordingly based on every point percentage lower than 85%.This situation may repeatedly happen on the succeding energy bills of power customer.The power customer is desired to improve its historical power factor of 0.67 lagging and no further penalty be impose by the local power company on the next bill. Q: Identify the appropriate solution you want to offer to Client?.Justify SCIENTIFICALLY and MATHEMATICALLY the principles behind the solution.
Which modulation has higher data rates a.fm b.am c.qam d.qpsk
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)