Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how to calculate the wind pressure



how to calculate the wind pressure..

Answer / hbeebur rahman

Wind pressure at any height above ground level shall be
obtained by following relation,Pz=0.6Vz^2.
where,
Pz=wind pressure
Vz=design wind speed
Vz=Vb*K1*K2*K3,
Where,
Vb=wind speed at particular place,
k1=risk co efficient
k2=terrain category
k3=topography factor
(for k1,k2,k3 values use is875 part3)

Is This Answer Correct ?    12 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what could be the production cost of 1 cum of concrete by CP30 plant

0 Answers   GDC,


Why you are leaving present job?

0 Answers   HCL, L&T, NCC,


Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever

0 Answers  


WHAT TYPE OF BINDING WIRE IS USED IN OFF SHORE STRUCTURES. WHEATHER COROSIVE OR NON COROSIVE LIKE EPOXY COATED,PLASTIC COATED ETC.

1 Answers  


Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)

0 Answers   L&T, Shoba Devlopers,


what will be hook length of stirrups

7 Answers   Rawabi Fayfa,


what is the minimum SBC of soil is required for different types of soil?

1 Answers  


Highest compressive strength of M15 concrete that can be gained at 28 days

3 Answers  


What is the purpose of the gap in the road on this bridge?

0 Answers  


what is the standard gradient or slope for drainage?

1 Answers   IGC, SPL,


what is preposition of M-5 grade

3 Answers   Montag Infrastructure,


silt%= silt volume/ silt+sand volume is this right?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)