Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how the calculation is done if the DG set require for the --
-48 to -51v 4000 ah battery set .



how the calculation is done if the DG set require for the -- -48 to -51v 4000 ah battery set ...

Answer / k.prakashchandra

Generally ,the charging rate should be at least 10 % of AH
of the battery set numerically,so that full charging time
will not exceed 10 hours.

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

What are the types of relay ?

3 Answers  


Please elaborate th´evenin’s theorem?

0 Answers  


Why PT voltages are measured with respect to ground? What do u mean by voltage or current polarized.

0 Answers   Grasim,


difference between ceiling fan

24 Answers   Altius Technologies, Raisoni, TCS, Uni Deritend,


How core saturation effects the secondary voltage (whats the theory) of a current transformer in service?

1 Answers  


wat system call?

0 Answers  


Why synchronous motor runs at a fixed speed? what is the name of that fixed speed?

4 Answers  


how can i use REF and diffrencial relay both in 1 CT core for transformer protection?

0 Answers  


when qty of cable being purchased is not sufficient according to the standard,what should the inspector do to ensure its quality according to the standard?

0 Answers  


How to size Air Circuit breaker (ACB)? What is the most important factors?

0 Answers   ABC,


How to design harmonic filter at the project stage without nowing the harmonics levels

0 Answers  


trasformer ratting

2 Answers   Bhel,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)