You have 8 balls. One of them is defective and weighs less
than others. You have a balance to measure balls against
each other. In 2 weighings how do you find the defective one?
Answers were Sorted based on User's Feedback
Answer / balbir singh
Firstly we take 6 balls, placing 3 on each pan of the
balance & check which pan goes up(1st weighing). If no
change it means the balls don't contain the defective
one,therefore the other two contain the defective
ball,which can be found out easily(2nd weighing).
Now if one of the pan goes up,it means it contains the
defective ball(out of 3 balls).We select these 3 & unload
the pans. Now we keep any of the 2 balls(from the selected
balls)on either side of the balance & weigh(2nd weighing).
One of these two will be the defective one and if not the
3rd one leftover is.
| Is This Answer Correct ? | 67 Yes | 6 No |
Answer / savitha shreyas
Firstly we take 6 balls, placing 3 on each pan of the
balance & check which pan goes up(1st weighing). If no
change it means the balls don't contain the defective
one,therefore the other two contain the defective
ball,which can be found out easily(2nd weighing).
Now if one of the pan goes up,it means it contains the
defective ball(out of 3 balls).We select these 3 & unload
the pans. Now we keep any of the 2 balls(from the selected
balls)on either side of the balance & weigh(2nd weighing).
One of these two will be the defective one and if not the
3rd one leftover is.
| Is This Answer Correct ? | 20 Yes | 2 No |
Answer / abi
Firstly we take 6 balls, placing 3 on each pan of the
balance & check which pan goes up(1st weighing). If no
change it means the balls don't contain the defective
one,therefore the other two contain the defective
ball,which can be found out easily(2nd weighing).
Now if one of the pan goes up,it means it contains the
defective ball(out of 3 balls).We select these 3 & unload
the pans. Now we keep any of the 2 balls(from the selected
balls)on either side of the balance & weigh(2nd weighing).
One of these two will be the defective one and if not the
3rd one leftover is.
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / aby
Firstly we take 4 balls, placing 2 on each pan of the
balance & check which pan goes up(1st weighing). If no
change it means the balls don't contain the defective
one,therefore the other Group of 4 balls contain the
defective
ball,Now if one of the pan goes up,it means it contains the
defective ball(out of 2 balls).We select these 2 & unload
the pans. Now we keep 1 ball(from the selected
balls)on either side of the balance & weigh(2nd weighing).
One of these two will be the defective one otherwise it
must b in the second group of balls.
| Is This Answer Correct ? | 3 Yes | 11 No |
Answer / rajeev kumar
Solution:
a. first take 4-4 group of balls and weight this. Then one
of group will be less.
b. next we take less weight group and take 2-2 group and
weight this and choose less weight group.
c. next take 1-1 group and weight choose less weight group.
and there is one ball.
So this ball is defective ball.
| Is This Answer Correct ? | 6 Yes | 25 No |
Travelling for 9 days. total dist to be covered is 1080 miles. Dist covered per day must be 20 miles then that of previous day. what dist is covered
i want to know the aptitude qs of hsbc bank
0 Answers Bank Of America, HSBC,
the program size is N. the memory occupied by the program is M=4000sqrt(N).if the program size is incresed by 1%.then what is the percentage increase in memory.
Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men work to complete the job? (a) 8 hrs (b) 7 1/2 hrs (c) 7 hrs (d) 9 hrs
35 Answers Atos Origin, ATS, College School Exams Tests, Entech, Four soft, HCL, IBM, IMS, Infosys, Kekran Mekran, L&T, ProKarma, Sree Nakshatra, State Bank Of India SBI, Subix, Sunera Technologies, Syntel, TCS, Tech Mahindra, TechMind, TransWorks, Unisys,
A telephone cable is to be run from a junction point on the bank of a river 900 meters wide to an office that is located 3000 meters downstream on the opposite bank. If the cost of laying cable under water is Rs. 5 per meter and that of laying overhead on land is Rs. 4 per meter, find the point downstream where the cable is to cut across the river. (a) 450 (b) 1800 (c) 2800 (d) 2100 (e) 2700
2) If A, B and C are the mechanisms used separately to reduce the wastage of fuel by 30%, 20% and 10%. What will be the fuel economy if they were used combined.
How many people are there in the queue if I am 7th in the queue from either end?
I belongs to OBC candidate, got admission in Deemed university (MAHARASHTRA) shall I got freeship. pl clarify,
a cylinder ingot 6cms in diameter and 6 cms in height is and spheres all of the samesize are made from the material obtained.what is the diameter of each sphere?
if area is icc. by 30% then what is the change in the area?
I am writing the APSRTC OUT post.so i dont know the managerial aptitude.If any one know about this or refer any book, please give the information to my Mail id is narayanansg@gmail.com
6:60::?:504