The application test plans are developed in which of the
following systems development life cycle (SDLC) phases?
A. Design
B. Testing
C. Requirement
D. Development
Answer / guest
Answer: A
Developing test plans for the various levels of testing is
one of the key activities during the application development
design phase. The test plans are used in the actual software
testing.
| Is This Answer Correct ? | 6 Yes | 0 No |
An IS auditor, in evaluating proposed biometric control devices reviews the false rejection rates (FRRs), false acceptance rates (FARs) and equal error rates (ERRs) of three different devices. The IS auditor should recommend acquiring the device having the: A. least ERR. B. most ERR. C. least FRR but most FAR. D. least FAR but most FRR.
One of the purposes of library control software is to allow: A. programmers access to production source and object libraries. B. batch program updating. C. operators to update the control library with the production version before testing is completed. D. read-only access to source code.
Which of the following procedures would BEST determine whether adequate recovery/restart procedures exist? A. Reviewing program code B. Reviewing operations documentation C. Turning off the UPS, then the power D. Reviewing program documentation
52. Which of the following tests confirm that the new system can operate in its target environment?
A programmer included a routine into a payroll application to search for his/her own payroll number. As a result, if this payroll number does not appear during the payroll run, a routine will generate and place random numbers onto every paycheck. This routine is known as: A. scavenging. B. data leakage. C. piggybacking. D. a trojan horse.
Which of the following is a check (control) for completeness? A. Check digits B. Parity bits C. One-for-one checking D. Prerecorded input
Is it appropriate for an IS auditor from a company that is considering outsourcing its IS processing to request and review a copy of each vendor's business continuity plan? A. Yes, because the IS auditor will evaluate the adequacy of the service bureau's plan and assist his/her company in implementing a complementary plan. B. Yes, because, based on the plan, the IS auditor will evaluate the financial stability of the service bureau and its ability to fulfill the contract. C. No, because the backup to be provided should be specified adequately in the contract. D. No, because the service bureau's business continuity plan is proprietary information.
An IS auditor is performing an audit of a network operating system. Which of the following is a user feature the IS auditor should review? A. Availability of online network documentation B. Support of terminal access to remote hosts C. Handling file transfer between hosts and inter-user communications D. Performance management, audit and control
Which of the following physical access controls would provide the highest degree of security over unauthorized access? A. Bolting door lock B. Cipher lock C. Electronic door lock D. Fingerprint scanner
Which of the following protocols would be involved in the implementation of a router and interconnectivity device monitoring system? A. Simple network management B. File transfer C. Simple Mail Transfer Protocol D. Telnet
After implementation of a disaster recovery plan (DRP), pre-disaster and post-disaster operational cost for an organization will: A. decrease. B. not change (remain the same). C. increase. D. increase or decrease depending upon nature of the business.
Which of the following types of transmission media provide the BEST security against unauthorized access? A. Copper wire B. Twisted pair C. Fiber-optic cables D. Coaxial cables