Describe V Model with the entry criteria of each Test Phase.



Describe V Model with the entry criteria of each Test Phase...

Answer / vijay rao

CUSTOMER S/W RELEASED TO CLIENT
| ^
v |
CRS ------------- Review CRS -------------> ACCEPTENCE T'ING
| write ACCEPTENCE test plan(ATP) ^
| write ACCEPTENCE test case(ATC) |
v |
SRS ------------- Review SRS against CRS---> SYSTEM TESTING
| write SYSTEM test plan(STP) ^
| write SYSTEM test case(STC) |
v |
HLD ------------- Review HLD -----------> INTERGRAION T'ING
| write INTEGRATION test plan(ITP)^
| write INTEGRATION test case(ITC)|
v |
LLD ------------- Review LLD -----------> FUNCTIONAL T'ING
| write FUNCTIONAL test plan(FTP) ^
| write FUNCTIONAL test case(FTC) |
v |
CODING----------------------------------> UNIT TESTING OR
WHITE BOX TESTING

(DEVELOPMENT TEAM) (TESTING TEAM)


Hence it looks like V we call it V model or V-V model also.

CRS -- CUSTOMER REQUIRMENT SPECIFICATION
SRS -- SOFTWARE REQUIRMENT SPECIFICATION
HLD -- HIGH LEVEL DESIGN
LLD -- LOW LEVEL DESIGN
BA -- Business Analyst
WBT -- White Box Testing
BBT -- Black Box Testing

I wl explain you in brief how it works with advantages and
disadvantages in simple language.

Left hand side of the model is taken care by Dev, and other
half by Testers. we also call it Verification and
Validation model.

1st phase - When BA collects the CRS from client,it is
given to Dev team and as well as to testing team. Dev
starts developing the SRS where as testing team review the
crs and mean time they start writing ATP,ATC...
If testers come up with any mistakes in crs say
a) Conflict in requirment
b) Missing requirment
c) Wrong requirment
These bugs is communicated to Dev and it is clarified with
BA and client once again.. once the changes is made to crs,
it is again send to testing team.. Dev will make sutiable
modifications in SRS hence they already started developing
it. The same procedure continues untill Testing Team (TT)
approves it.

2nd phase - By that time Dev are ready with SRS, they give
it to TT and they start developing the HLD.
Testers review SRS against CRS and find the bugs,if any, it
is send to Dev, they fix it and resend it to testers, they
make modifications in HLD. Procedure continues untill SRS
is bug free,they write STP,STC.

3rd phase - Similarly as 2nd

4th phase - once coding is ready, developers perform Unit
testing or WBT, where they test each and every line of code.
Types are -> Path Testing
-> Condition Testing
-> Loop Testing
-> Memory Testing
-> Performance Testing

Remaining FT,IT,ST,AP are called BBT done by testers.

Advantages are :--

a) Testing starts from initial stage of development and
every stages are tested.
b) Tesing the Requirment avoids downward flow of defects
C) Deliverables are parallel and simultaneous,so project
will complete in lesser time
d) Total investment is less
E) Requirment changes are handled easily and efficiently.

Dis advantages are :--

a) The model involves lot of documentation work
b) Intitial investment is more

We can go for this model:
a) Long term projects
b) complex projects
c) high quality prodcut within sitpulated time frame

Is This Answer Correct ?    18 Yes 1 No

Post New Answer

More Manual Testing Interview Questions

What is the difference between SRS and BRS

5 Answers  


why RUPis important or what are all the advances in RUP?

1 Answers  


Hi,friends i am going to write ICST certificate exam on augest.So can anybody post some of sample qusetions for ICST certificate exam.Really it will be useful for me

0 Answers  


what is test case review?

3 Answers   Zenith,


how to report reviews

2 Answers   Tech Mahindra,






How can a testengineer coordinate with developer in fixing bugs?

1 Answers  


diffrence between defect and bug life cycle

3 Answers  


Hi, I got an offer with maveric systems and I have around 3.5 years of work experience. But inspite of that they are asking to sign a bond for 2 years and to pledge all the original certificates for that bond. Can anybody please advice me whether its a good company or not and can i go ahead with this?

4 Answers   Marveric,


what are the factor taken under website testing manually?

3 Answers  


Give me 2 examples for - High Priority with Low Severity? And - High Severity with Low Priority??

1 Answers   Infosys, Mastek, SunGard,


How to perform the end to end testing or system testing for the Railway ticket booking application?

1 Answers   HCL,


How do you determine user load for a performance test of a Web application?

0 Answers  


Categories