In planning a software development project, which of the
following is the MOST difficult to determine?

A. Project slack times

B. The project's critical path

C. Time and resource requirements for individual tasks

D. Relationships that preclude the start of an activity
before others are complete



In planning a software development project, which of the following is the MOST difficult to determi..

Answer / guest

Answer: C

"The most difficult problem is effectively estimating a
project's slack time and/or resource requirements for
individual tasks or development activities. This commonly is
done through direct software measures (size-oriented
SLOC-source lines of code

KLOC-thousand lines of code) or indirect software measures
(function points-values for number of user inputs, outputs,
inquiries

number of files and interfaces). The other choices are
project management methods and techniques employed that are
dependent on the effectiveness of methods used in deriving
accurate and reliable software development productivity and
performance measures."

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

The use of residual biometric information to gain unauthorized access is an example of which of the following attacks? A. Replay B. Brute force C. Cryptographic D. Mimic

1 Answers  


An IS auditor who is participating in a systems development project should: A. recommend appropriate control mechanisms regardless of cost. B. obtain and read project team meeting minutes to determine the status of the project. C. ensure that adequate and complete documentation exists for all project phases. D. not worry about his/her own ability to meet target dates since work will progress regardless.

1 Answers  


Failure to adequately define or manage the requirements for a system can result in a number of risks. The GREATEST risk is: A. inadequate user involvement. B. inadequate allocation of resources. C. scope creep. D. an incorrect estimation of the critical path.

1 Answers  


While reviewing the business continuity plan of an organization, the IS auditor observed that the organization's data and software files are backed up on a periodic basis. Which characteristic of an effective plan does this demonstrate? A. Deterrence B. Mitigation C. Recovery D. Response

1 Answers  


The quality assurance group is typically responsible for: A. ensuring that the output received from system processing is complete. B. monitoring the execution of computer processing tasks. C. ensuring that programs and program changes and documentation adhere to established standards. D. designing procedures to protect data against accidental disclosure, modification or destruction.

1 Answers   Nest,






Involvement of senior management is MOST important in the development of: A. strategic plans. B. IS policies. C. IS procedures. D. standards and guidelines.

1 Answers  


The editing/validation of data entered at a remote site would be performed MOST effectively at the: A. central processing site after running the application system. B. central processing site during the running of the application system. C. remote processing site after transmission to the central processing site. D. remote processing site prior to transmission of the data to the central processing site.

1 Answers  


A debugging tool, which reports on the sequence of steps executed by a program, is called a/an: A. output analyzer. B. memory dump. C. compiler. D. logic path monitor.

2 Answers  


The difference between whitebox testing and blackbox testing is that whitebox testing: A. involves the IS auditor. B. is performed by an independent programmer team. C. examines a program's internal logical structure. D. uses the bottom-up approach.

1 Answers  


Which of the following is an example of the physiological biometrics technique? A. Hand scans B. Voice scans C. Signature scans D. Keystroke monitoring

2 Answers  


Which tests is an IS auditor performing when certain program is selected to determine if the source and object versions are the same?

4 Answers  


An IS auditor is reviewing a project that is using an agile software development approach. Which of the following should the IS auditor expect to find? A. Use of a capability maturity model (CMM) B. Regular monitoring of task-level progress against schedule C. Extensive use of software development tools to maximize team productivity D. Postiteration reviews that identify lessons learned for future use in the project

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)