In planning a software development project, which of the
following is the MOST difficult to determine?

A. Project slack times

B. The project's critical path

C. Time and resource requirements for individual tasks

D. Relationships that preclude the start of an activity
before others are complete

Answer Posted / guest

Answer: C

"The most difficult problem is effectively estimating a
project's slack time and/or resource requirements for
individual tasks or development activities. This commonly is
done through direct software measures (size-oriented
SLOC-source lines of code

KLOC-thousand lines of code) or indirect software measures
(function points-values for number of user inputs, outputs,
inquiries

number of files and interfaces). The other choices are
project management methods and techniques employed that are
dependent on the effectiveness of methods used in deriving
accurate and reliable software development productivity and
performance measures."

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

purchase orders issued to vendors have been authorized as per the authorization matrix

1093


WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2843