Following a reorganization of a company's legacy database,
it was discovered that records were accidentally deleted.
Which of the following controls would have MOST effectively
detected this occurrence?
A. Range check
B. Table lookups
C. Run-to-run totals
D. One-for-one checking
Answer / guest
Answer: C
Run-to-run totals would have been an effective detective
control over processing in this situation. Table lookups and
range checks are used for data validation before input, or
as close to the point of origination as possible.
One-for-one checking is time consuming and therefore less
effective.
| Is This Answer Correct ? | 7 Yes | 0 No |
An IS auditor should be concerned when a telecommunication analyst: A. monitors systems performance and tracks problems resulting from program changes. B. reviews network load requirements in terms of current and future transaction volumes. C. assesses the impact of the network load on terminal response times and network data transfer rates. D. recommends network balancing procedures and improvements.
Which of the following is the MOST important reason for an IS auditor to be involved in a system development project? A. Evaluate the efficiency of resource utilization. B. Develop audit programs for subsequent audits of the system. C. Evaluate the selection of hardware to be used by the system. D. Ensure that adequate controls are built into the system during development.
An IS auditor is conducting substantive audit tests of a new accounts receivable module. The IS auditor has a tight schedule and limited computer expertise. Which would be the BEST audit technique to use in this situation? A. Test data B. Parallel simulation C. Integrated test facility D. Embedded audit module
Which of the following is MOST likely to occur when a system development project is in the middle of the programming/coding phase? A. Unit tests B. Stress tests C. Regression tests D. Acceptance tests
An installed Ethernet cable run in an unshielded twisted pair (UTP) network is more than 100 meters long. Which of the following could be caused by the length of the cable? A. Electromagnetic interference (EMI) B. Cross talk C. Dispersion D.Attenuation
Responsibility and reporting lines cannot always be established when auditing automated systems since: A. diversified control makes ownership irrelevant. B. staff traditionally change jobs with greater frequency. C. ownership is difficult to establish where resources are shared. D. duties change frequently in the rapid development of technology.
The responsibility, authority and accountability of the IS audit function is documented appropriately in an audit charter and MUST be: A. approved by the highest level of management. B. approved by audit department management. C. approved by user department management. D. changed every year before commencement of IS audits.
The MAJOR advantage of the risk assessment approach over the baseline approach to information security management is that it ensures: A. information assets are over protected. B. a basic level of protection is applied regardless of asset value. C. appropriate levels of protection are applied to information assets. D. an equal proportion of resources are devoted to protecting all information assets.
After implementation of a disaster recovery plan (DRP), pre-disaster and post-disaster operational cost for an organization will: A. decrease. B. not change (remain the same). C. increase. D. increase or decrease depending upon nature of the business.
Which of the following reports should an IS auditor use to check compliance with a service level agreement (SLA) requirement for uptime? A. Utilization reports B. Hardware error reports C. System logs D. Availability reports
Digital signatures require the: A. signer to have a public key and the receiver to have a private key. B. signer to have a private key and the receiver to have a public key. C. signer and receiver to have a public key. D. signer and receiver to have a private key.
Which of the following goals would you expect to find in an organization's strategic plan? A. Test a new accounting package. B. Perform an evaluation of information technology needs. C. Implement a new project planning system within the next 12 months. D. Become the supplier of choice within a given time period for the product offered.