You are the test manager starting on system testing. The
development team says that due to a change in the
requirements, they will be able to deliver the system for
SQA 5 days past the deadline. You cannot change the
resources (work hours, days, or test tools). What steps
will you take to be able to finish the testing in time?
Answers were Sorted based on User's Feedback
Answer / neelima
1. priortise the tests based on the requirements
criticality,complexity, end user stressed .
2. check with the developers about what requirements are
going to be changed and how many tests are going to be
effected due to that.
3.check with the project manager to defer any of the
functionality testing for later .
4. check with the developers how thorough that their
modules are tested .
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / amit verma
-Ask the Developers or Refer FRS in which module he had
done the changes then according to that prepare Test
Scenarious and then execute them accordingly.
-Perform Sanity and System Testing
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / saff5005
in this situvation i will change the scope of the testing
to fit the deadline andinclude those feature which are most
imp and have high impact on business
Is This Answer Correct ? | 1 Yes | 0 No |
why ur Looking for Change?(In P.M)
can you tell me test case for whatsapp?
7 Answers AFour Technologies, InfoBeans,
hi one of the interviewer asked me have you ever created a test plan?
I attended an interview for Testing as a fresher, I said I already had project training, they asked me if I found anything difficult while testing or preparing test cases, one other question was if I am given the same test cases again the next day will it be a waste of time. Really I dont know what answers they expect please help.
What is test plan and contents available in a test plan?
Explain stub in testing point of view?
What type of testing you are doing ?
Can someone explain integration testing with examples?
What do you mean by review? How many reviews are there in manual testing? please explain those?
what is verification and validation,
what is smoke testing? what is sanity testing?
After recieved the defect from Tester,developer is not getting any error while executing that bug then he will reject that defect due to the above reason.As a Tester what we can do in that situation?