Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


You are the test manager starting on system testing. The
development team says that due to a change in the
requirements, they will be able to deliver the system for
SQA 5 days past the deadline. You cannot change the
resources (work hours, days, or test tools). What steps
will you take to be able to finish the testing in time?

Answers were Sorted based on User's Feedback



You are the test manager starting on system testing. The development team says that due to a chang..

Answer / neelima

1. priortise the tests based on the requirements
criticality,complexity, end user stressed .
2. check with the developers about what requirements are
going to be changed and how many tests are going to be
effected due to that.
3.check with the project manager to defer any of the
functionality testing for later .
4. check with the developers how thorough that their
modules are tested .

Is This Answer Correct ?    5 Yes 0 No

You are the test manager starting on system testing. The development team says that due to a chang..

Answer / amit verma

-Ask the Developers or Refer FRS in which module he had
done the changes then according to that prepare Test
Scenarious and then execute them accordingly.
-Perform Sanity and System Testing

Is This Answer Correct ?    1 Yes 0 No

You are the test manager starting on system testing. The development team says that due to a chang..

Answer / saff5005

in this situvation i will change the scope of the testing
to fit the deadline andinclude those feature which are most
imp and have high impact on business

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Manual Testing Interview Questions

Suppose You are a Test Lead in your company. The dead line of project is next week.But the product have only 50 percent defect free.How you handle this situation?

7 Answers   HBS,


Diff between static and dynamic review?

3 Answers   Softdel,


Explain about Double V model?

3 Answers   AppLabs,


if bug is found & we will know the main Resion for that bug Arrise 1 - Corrective & Prevention Action 2 - Risk ana 3 - Root Cause analysis 4 - Impact analysis

5 Answers   NIIT,


As a testing engineer what to do if same defect is occured again in the software??

2 Answers  


What is the need of smoke test even when unit test is done by developers?

6 Answers  


write test cases forthe function f=a+b ?

2 Answers   Kanbay,


What is validation and verification? What is different between them?

8 Answers   Banking, Nedbank,


What knowledge I must have as a 3 yrs. manual tester??

0 Answers  


which test comes first installation testing or compatiability testing

7 Answers   ADP,


What is a Rad model?what are the advantages and disadvantages of rad model over the other sdlcs?

2 Answers  


Which method of testing we use to test LOGIN page?

10 Answers   Cap Gemini,


Categories