How do u calculate Schedule variance? What is the formula?
Explain with Example
Answer / abhishek tripathi
Schedule Metrics are related to variations between the
planned (base lined) schedule and actual schedule. Schedule
metrics basically provide you with schedule variance for
projects – scheduled completion, actual completion date and
the number of days of variance.
Schedule Variance = (Actual Duration-Planned Duration) /
(Planned Duration) * 100
| Is This Answer Correct ? | 4 Yes | 3 No |
What is code complete?
What and where are the policy statements that dictate quality assurance in your project?
A payroll system?
0 Answers E-Clear Technologies,
When does metrics validation occur? 1. Throughout the life cycle 2. During the test 3. After the test 4. During requirements definition 5. After the final software release Justify ur answer with simple explanation.
1 Answers Olenick, Sigmar, Vidyanikethan,
What is Deffered? explain it who allocate it?
How do you perform integration testing?
How is adhoc testing different from exploratory testing?
Hi all, I want to give ISTQB foundation level this july '08. PLease give me any question papers, syallabus, pateern type, books which u all have.. How long does one need to prepare. If you all have any data send it to karthis4u@gmail.com 9986667831
Q. How do you select product components for validation?What are the contents of QMS?
In testing what is the flow of testing AUT, like what test is to performed first and second test and soon Can Anyone list the sequence of testing
What is basis set?
What is the difference between 'Bug' and 'Issue'?