How do you calculate qty for form work like props shuttering
sheet and acro span for residential block ?
for Example: 10 sq mt what is the material and qty require to
do form work.

Answers were Sorted based on User's Feedback



How do you calculate qty for form work like props shuttering sheet and acro span for residential b..

Answer / narayani upadhyay

I am not sure too much about it, but it gives an idea for calculating the props , number of sheets and acrospane in a building form work.
size of ms sheet (steel sheet)= 2' * 3'=6 6sqft
props should be between 500 mm to 600 mm to each-other.
Acrospane are uses from one end to other end for supporting the ms sheet on slab.
lets assume the size of 2 BHK = 1000 sqft
=Number of sheet required =1000/6=166.67 approx=170
Add 10 to 15 % wastage=170*1.10=187
=If depth of slab less than 175 mm = 4 sheet contain 1 acrospane.
= If depth of slab more than 175 mm=5 sheet contain 1 acrospan
= lets assume depth of slab= 125 mm
= Number of acrospane= 187/4=46.75 approx=50
=number of props requred= it depend on the size of beam and length of beam around the slab.Total length of beam in running meter around the slab(incuding sunken,balcony ,ots and staircase)=70 m
=props should be between 0.5 m to 0.6 m.
=number of Props for BEAM length=70/0.6=116=approx 120
=Number of props for slab=50*2=100
= Total number of PROPS=320

Is This Answer Correct ?    26 Yes 7 No

How do you calculate qty for form work like props shuttering sheet and acro span for residential b..

Answer / thamaraikani

simple constructin material calculation:
sheet,span and props
assuming :1000sqm builtup area
step1:sheet
1000/0.9*0.6=1851nos
step2:span
note:(slab thickness less than 175=4sheet)
(slab thickness more than175=5sheet)
span=1851/5=370nos
step3:props
note:(slab thickness less than 175=4sheet/2)slab thickness less than 175=5sheet/2)
props=370*2.5=925nos

Is This Answer Correct ?    6 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

Why are L-beams (cast monoloithic with slab)that usually occur at the slab edge, provided with overhangs?

1 Answers  


What happens to Load at yielding ?

0 Answers  


how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?

0 Answers  


How to calculate brick work quantity?? Block work quantity??

0 Answers   Brigade,


how to calculate the density for high density concrete ? or is it same as the density of RC?

0 Answers   Gammon,






why provide water stopper in costruction joits

1 Answers   L&T,


what is idealized curve for concrere and steel

0 Answers   CSIL,


Where is lap in top & bottom beam

1 Answers   Bucon Infratech,


why breadth of beam is shorter than (or equal to )its depth?

8 Answers   CCCL,


1.DIFFERENCE BETWEEN NOMINAL MIX AND DESIGN MIX? 2.WHAT IS MEANT BY STRUCTURAL DESIGN? 3.IN STAAD WHY WE RELEASE MOMENT TO A MEMBER? 4.ON WHAT BASIS PARTIAL FACTOR OF SAFETY ARE DECIDE?FROM THE LOAD COMBINATION? 5.WHY WE PROVIDE EXTRA BAR & DEVELOPEMENT LENGTH AT TOP? 6.FULL FORM OF SPT & SMB? 7.WHAT IS MEANT BY ITP IN A CONSTRUCTION PROJECT? 8.WHAT IS LEAST COUNT OF THEODOLITE SURVEY? 9.WHAT ARE THE CAUSES OF FAILURE OF FOUNDATIONS AND REMEDIAL MEASURES? 10.WHAT ARE THE VALUES OF COMPRESSIVE STRENGTH? 11.STEEL CALCULATION FOR FOOTING,BEAM & SLAB? 12.WHAT IS MEANT BY GANTRY GIRDER? 13.IN SITE HOW WE CAN IDENTIFY THE ONE WAY, TWO WAY SLAB? 14.DIFFERENCE BETWEEN ANCHORAGE LENGTH & DEVELOPEMENT LENGTH? 15.BEARING CAPACITY OF STEEL SHUTTERING?LOAD CARRYING FOR SHUTTERING?

3 Answers  


what is pile cap and why its used ??? why its provided in different shape

2 Answers  


How to get cinema chance?

78 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)