How do you calculate qty for form work like props shuttering
sheet and acro span for residential block ?
for Example: 10 sq mt what is the material and qty require to
do form work.
Answers were Sorted based on User's Feedback
Answer / narayani upadhyay
I am not sure too much about it, but it gives an idea for calculating the props , number of sheets and acrospane in a building form work.
size of ms sheet (steel sheet)= 2' * 3'=6 6sqft
props should be between 500 mm to 600 mm to each-other.
Acrospane are uses from one end to other end for supporting the ms sheet on slab.
lets assume the size of 2 BHK = 1000 sqft
=Number of sheet required =1000/6=166.67 approx=170
Add 10 to 15 % wastage=170*1.10=187
=If depth of slab less than 175 mm = 4 sheet contain 1 acrospane.
= If depth of slab more than 175 mm=5 sheet contain 1 acrospan
= lets assume depth of slab= 125 mm
= Number of acrospane= 187/4=46.75 approx=50
=number of props requred= it depend on the size of beam and length of beam around the slab.Total length of beam in running meter around the slab(incuding sunken,balcony ,ots and staircase)=70 m
=props should be between 0.5 m to 0.6 m.
=number of Props for BEAM length=70/0.6=116=approx 120
=Number of props for slab=50*2=100
= Total number of PROPS=320
| Is This Answer Correct ? | 26 Yes | 7 No |
Answer / thamaraikani
simple constructin material calculation:
sheet,span and props
assuming :1000sqm builtup area
step1:sheet
1000/0.9*0.6=1851nos
step2:span
note:(slab thickness less than 175=4sheet)
(slab thickness more than175=5sheet)
span=1851/5=370nos
step3:props
note:(slab thickness less than 175=4sheet/2)slab thickness less than 175=5sheet/2)
props=370*2.5=925nos
| Is This Answer Correct ? | 6 Yes | 3 No |
how to calculate the density for high density concrete ? or is it same as the density of RC?
How foundation is designed, Column design and beam design
What is used for 1cubicmeter steel ? 1meter length square pipe how many weight ?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
24. Why should we hire you?
Hai, I have applied for APPSC AEE (I&CAD) post.I need previous AEE papers of civil engineering.I hope u will kindly consider this and send.
how many material required for brickbat water proofing of toilets.
What is the usage of zoom command?
what is the difference between rise and tread? what is its standered size? what is waist slab?what is the standered length of staire-case? also what is the angle between floor and landing?
how do you measure the 1:2:4 and 1:1:2 proportion rcc concrete for one cubic metre? what is the cement qty. sand qty. jelly qty.
Which is the direction of negative angle?
Which are the Steel tests ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)