How do you calculate qty for form work like props shuttering
sheet and acro span for residential block ?
for Example: 10 sq mt what is the material and qty require to
do form work.
Answer Posted / thamaraikani
simple constructin material calculation:
sheet,span and props
assuming :1000sqm builtup area
step1:sheet
1000/0.9*0.6=1851nos
step2:span
note:(slab thickness less than 175=4sheet)
(slab thickness more than175=5sheet)
span=1851/5=370nos
step3:props
note:(slab thickness less than 175=4sheet/2)slab thickness less than 175=5sheet/2)
props=370*2.5=925nos
| Is This Answer Correct ? | 6 Yes | 3 No |
Post New Answer View All Answers
How to calculate woden area in sft and Cft
What Are The Steps Involved In The Concreting Process, Explain?
what are the challenges of being a team leader and a supervisor?
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
Which tests are performed on soil to decide the type of foundation to be provided.
is basic cost of the material includes tax?
How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
material required for construction of 1cu.mtr wall (Cement, No of bricks (Brick size 40cm x 20cm x 10cm),sand,Quantity of water
What are wooden shingles?
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
cause of cylinder test failure
Why we provide hair pin for shed
What is quantity of cement and sand required for 2000sqft of tiling?