simple constructin material calculation:
sheet,span and props
assuming :1000sqm builtup area
step1:sheet
1000/0.9*0.6=1851nos
step2:span
note:(slab thickness less than 175=4sheet)
(slab thickness more than175=5sheet)
span=1851/5=370nos
step3:props
note:(slab thickness less than 175=4sheet/2)slab thickness less than 175=5sheet/2)
props=370*2.5=925nos

Is This Answer Correct ?    6 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

plumbing CPVC fitting FTE Brass full form

2136


what is kribs is supporting?

1600


what is the dimensions of river sand truck trailer or trolly ?

3381


For what building Built-on balconies are preferable? What are the advantages?

725


How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)

1738






How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel

1391


Explain what is change order request?

685


what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982

1670


where can i get the previous question papers for rrb section enginerr (civil)

1872


What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?

1854


What is the difference between EPC,DBOOT and BOOT.

23382


What is progress payment?

714


if we use 1.25 bag of cement 3 pharma metal and 2 pharma crush sand what is the strenghtexpected for RCC column

1618


Use of coping on terrace wall and in 4" wall is compulsory or not ?

1104


explain five benefits of using standard terminology in the measurement process?

1579