how to calculate the weight of 6mm dia rod
Answers were Sorted based on User's Feedback
Answer / amarjeet
generly it is calculated by d*d/162. for 1 m length. like
8dia bar: d*d/162= 8*8/162=
64/162 =0.395kg per meter length
if u t having 12 m rod of 8 mm dia than total weight of 12
m bar is= 12*0.395
= 4.74kg
| Is This Answer Correct ? | 26 Yes | 5 No |
Answer / sard
Find the volume of one metre length of rod . Multiply it
with desity ..
Often steel rods are weighed to make sure that no hollow
blow holes are there in manufactured steel
For each dia rods weight per unit metre is known and we can
weigh it properly
| Is This Answer Correct ? | 18 Yes | 3 No |
Answer / mohsin
d*d/162.162 where d is dia of bar.... remember it is weight
per meter..... like 6*6/162.162 = 0.222 kgs/meter....
8*d*d/3 where d is dia (in inches) of bar in FPS system...
d*d/24 also in FPS but here d is bar number... like #4 bar
mean 4/8 inch (0.5 inch)
| Is This Answer Correct ? | 11 Yes | 1 No |
Answer / bkaskarrao
Dia of road*Dia of road/162*length of road meter
ex:-8*8/162*1m
=0.395kg
ex;-8*8/162*12m
=4.74kg
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / shubham jain
Volume×density=weight
(Volume=area×length mm^3)
for 1m of length
((22×r×r÷7)×1000)mm^3=volume
(Volume = 3142.857 r×r=785.714 d×d mm^3)
(Density=7856.34×10^-9kg/mm^3)
Weight= 785.714×d×d×7856.34×10^-9 kg/m
Weight=d×d×6.17283726×10^-3 kg/m
Or
weight=d×d÷
For example :- 8mm steel bar
weight=8×8÷162 kg/m
WEIGHT= 0.395 kg/m
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / amit
the we use d*d/162 but the original formula where it is derived from is
take 1mm rod as
the sample
-----
| |
| |
| |
| |
----- aassume it as cyinder
and try calculating the area using
22/7*r*r*h
| Is This Answer Correct ? | 1 Yes | 4 No |
when we select buildup beam
what is anchorage length,lap length and (dont remember the last one)
Please let me know the name of university which is offered distance education in BE or Btech in direct 3rd samester????
Is it possible 18" beam rest on 18" beam and created the junction on beam instead of column?
for columns reinforcement the lap length is not provided then how to rebar the rods then how rebar should be lapped
4 Answers Nagarjuna Construction,
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
is there any influence of water(used for mixing of concrete) on a weight of harndend concrete.
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
Diversion of cum to cft
why there is no concrete mix of ratio 1:.5:1
How manu days after the casting of a slab another slab can be casted above it? what is the total curing time of a slab if ponding is not done on it?
what is plum concreting and how is it can be done what is the ratioo of rubble and concrete
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)