How do you arrive at the estimaton of efforts for a
particular function, if you have not worked on that
function testing before and do not have any past experience?
Answers were Sorted based on User's Feedback
Answer / shabana
The question is about estimation & not about the testing
strategy.
In can be drived based on following :
-------------------------------------
1.Based on the Functional Spec given
2.A rough estimation can be made based on the development
estimation given.(This is not preferred option but it helps)
3.It can also be based on the different integration points
with the AUT.
4.I guess a tester should be able to give an approx
estimation based on requirement analysis,funtional specs
Correct me if i am wrong.
Its truly good interview question.
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / honey
Actually estimation can be done with different techniques
and one of the technique would be WBS(Work breakdown
structure).
In this technique, we would
1. break down the funcitonalities into lower level
2. Identify the number of scenarios for each function
3. Prioritize them based on the complexity
4. Assign the time taken taken for High, Medium, Low
complex scenarios
5. Effort Estimates = Multiply the time taken with the
number of identified scenarios + 30% contigency
This is the answer I gave at the interview but the
interviewer was not satisfied and he was questioning
"What is the factor that you take into consideration for
estimating the time taken for the prioritized scenarios?"
Can anyone of you help me out with an answer?
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vk
All the above factors are valid ... In addition to that the
factors that one can consider for the development time
estimation are
- The number of Senior or Junior developers available with
in the development team. And based on the past projects
experience one can easily find out the average time taken by
each developer on the type of tasks assigned. So, now the
more complex tasks can be assigned to the developers who
have the minimum average time taken record. In this way one
can plan to finish all the development tasks at one time.
Please correct me If am not correct.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sarath
Actually we should not estimate for such things and should
take help of some one or explore similar feature or see the
mock screens to arrive at estimation
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / saket bharti
In this case we will use the data from previous project
whose nature and complexity of work are almost similar to
the new application.We shall give the estimates using those
data with a deviation margin of +-5%. This is the best
possible and accurate estimate which one can give in this
scenario.To be more accurate use the Work Breakdown
Structure to get the estimates on the lowest level of
activity and sum them all to give the final estimate.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / barsa
In this case we always start with +ve values (test the functionality by giving +ve values)then we go for -ve values.
2.There is no assumption should be made for requirement .
3.Testing is over when test engg feels maximum test coverage is done,i.e all +ve and -ve values are tested.
Is This Answer Correct ? | 0 Yes | 0 No |
What is Software Testing ? Why software testing is necessary ? When to stop testing?
what is difference between defect tracking and bugs tracking
How do we do Database testing?. How does our knowledge on SQL is useful in Database testing?. Please explain the process if possible.
is there any checklist to check SRS document
What is the major difference between database testing and datwarehouse testing ?
what is production defects?
What is Independant Testing? When and where this type of testing will be performed?
Can you explain decision tables?
hi everybody, iam Adi Durga, i complited my bsc(computers) in 2008.I have experience in finacial and bpo companys(mnc). but iam intersted on s/w role.I have the technical skills c, c++, Oracle 9i and manual testing. But i dont know hoe to strat my career in s/w. Every company offering on financial/bpo side. In this I attended nearly 10 companies,I selected in 8. All those are bpo and finacial, But i cant get any opportunities on s/w side.plz help how to get opportunites on s/w side. Actually I am interested on testing side. But every company offering for only experienced persons. plz help me. this is my mailid.... adi.durga19@gmail.com
What is the goal of Software Configuration Management(SCM? a.)Configuration Identifier b.)Configuration Control c.)Process Management d.)All options.
what is role of the tester in an organaisation and project? what is the daily work of tester?
What about manual testing opening in bangalore in September. Not getting a single interview call from last one month.