for 100sft of Cement plastering ratio 1:6 How much quantity
of cement and sand required.

Answers were Sorted based on User's Feedback



for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required...

Answer / ketan khetia

pls give detail that what is the thickness 6mm 12mm or 20mm
its depends on that
For 6 mm plaster cement use will be 0.25kg/sq.ft
for 12 mm plaster cement use will be 0.5kg/sq.ft
for 20 mm plaster cement use will be 1.0kg/sq.ft

Is This Answer Correct ?    111 Yes 17 No

for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required...

Answer / ahmed jaleel if any clarifica

100/3.28^2=9.29

1:6
The theekness of Plastering is 12mm

Sand is Requried in 1 cubic Mtr =1.25

Cement Is Requried In 1 cubic Mtr 1.25/6= .21

9.29 * .012 = .11148 * 0.21 =
.023 * 1440 = 33.71 Kgs Is Cement Requried.
( With Out Westage )

Sand = 1.25 * .023 = .02875 Cubic Mtr Sand Requried. ( With Out Westage )

Is This Answer Correct ?    60 Yes 16 No

for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required...

Answer / mohammed aijaz hussain

Let the thickness of Plastering be 12 mm.

Volume of Wet Mortar = 12mm X 100 sft.
= 12/ 1000 X 100/ 10.76
= 0.112 cu.m.

Add 20% for depressions, joints and wastage:

= 0.022 + 0112 = 0.134 cu.m.

Volume of Dry Mortar = 1.3 X 0.134 = 0.175 cu.m.

Cement required = 1/7 X 0.175 = 0.025 cu.m. = 0.71 Bag

Sand required = 6/7 X 0.175 = 0.15 cu.m.

Is This Answer Correct ?    41 Yes 21 No

for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required...

Answer / dushyant bansal

as per west baengal sor
10mm plaster 0.2cum cement and 1.2cum sand
15mm plaster 0.3cum cement and 1.8cum sand
20mm plaster 0.4cum cement and 2.4cum sand

Is This Answer Correct ?    22 Yes 17 No

for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required...

Answer / ashraf aslam

unit of rates=100 sft thickness of plaster let 1 inch wet volume of mortar=100*1/12=8.33 cft dry volume of mortar=8.33*1.27=10.58 cft {1.27 azafa dry vlm } ratio=1:6 sum of ratio=1+6=7 qnty of cmnt=1/6*10.58=1.76 cft or 1.76/1.25=1.41 bags qnty of snd=6/7*1o.58=9.068 cft

Is This Answer Correct ?    11 Yes 8 No

for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required...

Answer / vishal singh

12mm plaster 1 beg of cement & 7 cft sand

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

What are your goals?

1 Answers   Cisco, Flextronics, Hexaware,


how to calculate steel columns beams and slab please give me brief calculation

14 Answers   Focus, Haven Foundation, Indian Railways, Surya Builders, VICC,


What is the difference between Autodesk revit structure and STAAD pro.? How much it is useful to structural engineer in modelling, analysis & design of RCC and Structural steel structures than STAAD pro.?

3 Answers   L&T,


Can a 24" RCC beam can rest on 18" RCC beam.

2 Answers  


How to calculate the shuttering materials i.e MS sheet,Props,Acrow Spans,2'x3' Runner,4'x3' Runner & beam plywood bottom, sides in thumb rules in slab area

1 Answers   TATA,






General Knowledge 1. Which is the virus for SWINE Flu? Ans.H1N1 virus 2. Who is Paola Maino? a) Original Name of Sonia Gandhi. b) Mother Name of Sonia Gandhi c) An actress d) Christian Missionary 3. Who is Andy Moles? 4. Which state there is no scheduled caste seat for lok Sabha Assembly? CIVIL ENGINEERING 1. When was Indian road Congress (IRC) established? 2. What is the camber for Concrete Road? 3. What is the camber to be provided for Earth Road? 4. What is the ruling gradient to be provided for Plain roads? 5. What is the type of surveying to be used for deciding the alignment of hilly roads? 6. What is the condition on which Bernoulli law depends? 7. water is which type of fluid a)Newtonian b)Non- Newtonian c)Ideal d)Compressive 8. The law of continuity depends upon what factors? 9. In Plane Table surveying which is done first a) centering b)Leveling c)Orientation d)Centering and leveling simultaneously 10. Pavement width depends upon a)Type of terrain b) lane width c)Type of traffic 11. Which is costliest type of timber a) Sal b) Shish am c) Teak? 12. Which is timber used for making plywood a)Teak c) Bamboo fibers d)Common Timber 13. What is Veneering?

6 Answers   Vizag Steel, VSP,


how much steel required for 1 sq.m area?

12 Answers   L&T,


how to check the quality of concrete

3 Answers  


What is the soil bearing capacity ? And how it should be to built a multistory building ?

3 Answers   Clancy Networks, eConstruct, UltraTech,


Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

0 Answers  


why breadth of beam is shorter than (or equal to )its depth?

8 Answers   CCCL,


What are the different types of runners?

0 Answers   Bechtel,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)