for 100sft of Cement plastering ratio 1:6 How much quantity
of cement and sand required.
Answer Posted / vishal singh
12mm plaster 1 beg of cement & 7 cft sand
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
CAST EFFECTIVE WATER SUMP CONSTRUCTION DETAIL
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
Define absolute co-ordinates?
how i get all type of short type question answer about civil engg
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
Special thing in designing a overhead reservoir ? which is different from an ordinary design
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.
how many digree of freedom in four bar chain
what is Brest Wall?
What is Refuse Area In High Rise Building ?
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
what is cement wastage percentage in NHAI ROAD WORKS
How much quantity of cement Bag for block masonry (1:4) for 1 cu.m? Block size (150x200x400) Mortar Thickness 20mm
how many kg cement & fine sand reqird in one sq meter 1:6 mortar ratio?