what is role of tester in spiral model?



what is role of tester in spiral model?..

Answer / saurav

in spiral model we iterate through a no of self contained
development lifecycle...here delivery is devided into
increaments or built with each increament adding new
functionality...we as a tester we might b involved at
several level say as we hav check the intitial increament
to check all required functionality..subsequent increament
will need testing for new functionality,regression testing
of existing functionality and integration testing for both
existing and new functionality.....

Is This Answer Correct ?    10 Yes 0 No

Post New Answer

More Manual Testing Interview Questions

write 3 test cases on ATM for security purpose

8 Answers   Zycus Infotech,


What are the different criteria which will be filled when logging a Defect?

2 Answers   IBM, Sapient,


Can you explain the concept of fish bone/ Ishikawa diagram?

0 Answers  


When bug is raised ?

3 Answers   Amdocs,


which process u followed in ur company?

2 Answers  






What is the best way to answer, what is test scenario, strategy and test plan

1 Answers   Microsoft,


what is meant by alpha testing?

7 Answers   STC,


Test cases have written according to Flow of the software working or according to Screens?

0 Answers  


You are given two scenarios to test. Scenario 1 has only one terminal for entry and processing whereas scenario 2 has several terminals where the data input can be made. Assuming that the processing work is the same, what would be the specific tests that you would perform in Scenario 2, which you would not carry on Scenario 1?

2 Answers   IBM,


How will you prepare Test plan. What are the techniques involved in preparing the Test plan.

2 Answers   IBM, Wipro,


I HAV BEEN TO ONE INTERVIEW FEW DAYS BACK, tHEY ASK ME " TELL ME THE DIFFERENCE BETWEEN MANUAL & AUTOMATION TESTING" CAN ANYONE PLASE TELL ME THE PROPER ANS FOR THE SAME. THANK YOU

8 Answers   CitiGroup,


Suppose there are three modules A-B-C, the output of A is responsible for B and output of B is responsible for C and if A & C is not ready & B module is ready then how can u check Module B

4 Answers   TCS,


Categories