Q:What is the formula of bar to bent the slab in bent slab?
Second question Q: what is formula to calculate the hook?
Answers were Sorted based on User's Feedback
Answer / girish rawat
The bent up for end slab is L/7.
for continuous slab it is L/5.
For hooks it is 7x dia for each hook
| Is This Answer Correct ? | 16 Yes | 3 No |
Answer / sjtbehera
what is mean by bent slab. please explain. i know bend slab
( curtail renforcement) are provided. This is calculated by
l( effective length)/7.
hooks are normally calculated by 9d ( dia of Bar) or 14d
| Is This Answer Correct ? | 14 Yes | 5 No |
Answer / dhaval dhanani
l/5 continuous slab The bent up for end slab is L/7. For
hooks it is 7x dia for each hook
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / babu lal nayak
L/7 bent up length is ok for end slab...&
hook is 6xdia of bar
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / sridhar
every 45 degrees turn requires 4D
there fore hook 16D
| Is This Answer Correct ? | 1 Yes | 0 No |
What is unit weight of 1st class bricks ?
the beam size (450x1000) effective length is 19.0mts no intermediate supports and top 8nos 32dia and bot 32dia and condition is stragge lap. it is exceeding lap zones and exceed length of bars?
mix design of concrete using indian standard methods
One unit equal to how many brick
3 Answers Sainath Infrastructure,
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
how many kg reinforcement is required for G+ 1 roof slab of 1200qf slop slab with 5 inch thickness of house.
how to calculate the length diamond shaped striupps in column
It needs contour survey before plastering a wall / column & floor tiles setting to get––
how to calculate cutting length of stirrups bar in beam
If concrete fails in cube strength as well as non distactive test? what to do? for example grade of concrete is M35, cube strength is 26.1 n/mm2 after 28 days and non districtive test strength is 28.1 n/mm2 after 28 days. i am not distroying the rcc memeber.
What is the stripping time of shuttering for PPC concrete
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)