Q:What is the formula of bar to bent the slab in bent slab?
Second question Q: what is formula to calculate the hook?
Answer Posted / chanwill3
Bent up length for slab is 0.1L
hook for slab rod 4D
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.
What do you understand by “preset” during the installation process of bridge bearings?
What is Curtailing of R/F
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
how calucate cement sand ratio for plstering
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
I have an span length 16 ft c/c
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
at what pressure ply-wood is obtained by gluing wooden sheets
What are the benefits of rcc pipes over steel designed pipes?
What are the different types of foundation?
What are the Types Of DPC and its Thickness used?