A man, a woman, and a child can do a piece of work in 6
days. Man only can do it in 24 days. Woman can do it in 16
days and in how many days child can do the same work?
(WITH EXPLANATION)
Answers were Sorted based on User's Feedback
Answer / garima mishra
e=k/d
combined force=inividual force
let k=1 constant
1/6=1/24+1/16+1/x
1/x=1/24+1/16+1/6
1/x=16/96
1/x=1/6
so, x=6.
Is This Answer Correct ? | 8 Yes | 47 No |
What are the frequently asked technical engineer ques?
i made lan connections ,then how can i establish the network....with that connections only is the network is established ...tell me the procedure for giving the lan connection for some(10) pc's?
what is the difference between physical address and logical address?
MY interview Experience with TCS
why turbine vacuum breaker open in blackout
what is node class?
An integer number is said to be a perfect number if its factors, including 1 but not the number itself, sum to the number. For example, 6 is a perfect number because 6 = 1 + 2 + 3. Write a Java program, which finds and prints all perfect numbers that are less than 1600.
what is Networking?
nohup sort employees > list 2 > error out & what will happen?
what is the limitation of mis(management information system) report?
2 Answers ABS Construction, TATA,
what are the artifacts in coding phase in SDLC????
How to write AM/FM demodulation in C language ?