what is a project management?

Answers were Sorted based on User's Feedback



what is a project management?..

Answer / srinivasa rao paidisetti

Project Management is an Art & Science through which the
intended Products/Services are delivered with fixed
timelines, resources etc.

This is typically achieved through thorough planning,
execution finess, tireless monitoring & control. It is
also important that all the stakeholders are communicated
appropriately.

Is This Answer Correct ?    2 Yes 2 No

what is a project management?..

Answer / harinandan shaw

a project management has framework of operations to lead to
a successful completion of the project









harinandan shaw

Is This Answer Correct ?    1 Yes 1 No

what is a project management?..

Answer / atul

Project Management is a system to complete the task by
Initiating, Planning, Monitoring and controlling.

Is This Answer Correct ?    0 Yes 0 No

what is a project management?..

Answer / soma

Project Management is all about managing the project by delivering high quality product to customer with given timeline and cost. There are set of processes such as initiation, planning, executing, monitoring and controlling and closing helps to meet customer expectation.

Is This Answer Correct ?    0 Yes 0 No

what is a project management?..

Answer / shri

Initiating, planning, executing and controling and closure
of project.

Is This Answer Correct ?    0 Yes 3 No

what is a project management?..

Answer / joe

Project Management is to plan, execute and monitor as per
the process defined to complete the same as per the plan.

Is This Answer Correct ?    6 Yes 12 No

Post New Answer

More Project Management Interview Questions

The Project which is handled by you is in RED, customer has given you 4 weeks to show improvement, still nothing has worked out. The Customer again gives 3 weeks to improve and you do your best to improve, but nothing works out. Now the customer is not at all happy, HOW TO CONVINCE THIS CUSTOMER ???

8 Answers   AZS, BGR Energy, Wipro,


You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.

0 Answers  


The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

0 Answers  


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

0 Answers  


Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools

0 Answers  






Your procurement department has obtained independent estimates. The vendor's proposal is substantially different than the independent estimates. All of the following are true except: A. The SOW was not detailed enough. B. The vendor failed to respond according to the terms of the proposal. C. The vendor failed to respond to all items in the SOW. D. The vendor failed to respond to all items in the contract.

0 Answers  


What is the concept of project management?

0 Answers  


The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary

0 Answers  


what kind of questions can be asked from SDLC for a project leader role?

1 Answers   Satyam, TCS,


What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action

0 Answers  


what is a project management?

16 Answers   Areva, GB Engineering, Proteans,


how to handle project single handed?and what are the roles and responsibilities of a project leader?

4 Answers   Areva,


Categories