I have 1010 KVA Generator when i run the DG set for 5 to 6
hours the couplling (couplling joint in between engine &
alternator) bolts are getting loose what is the reason &
what is the remedy over this??????????

Answers were Sorted based on User's Feedback



I have 1010 KVA Generator when i run the DG set for 5 to 6 hours the couplling (couplling joint in..

Answer / cs reddy

Bolts are getting loose due to Vibration.
Vibrations may be due to :
a) Misallignment.
b) Improper foundation.
c) Improper Mass Balancing.

Is This Answer Correct ?    10 Yes 1 No

I have 1010 KVA Generator when i run the DG set for 5 to 6 hours the couplling (couplling joint in..

Answer / manoj saah

Coupling Misalligment may be major reason.

So do allignment by using Dial Gauge and clearance should
0.05 mm.

Is This Answer Correct ?    2 Yes 1 No

I have 1010 KVA Generator when i run the DG set for 5 to 6 hours the couplling (couplling joint in..

Answer / girish

Vibration is a main reason
1. Reduce vibration using vibration isolating mounts
2. use flexble coupling with lock nuts

Is This Answer Correct ?    1 Yes 0 No

I have 1010 KVA Generator when i run the DG set for 5 to 6 hours the couplling (couplling joint in..

Answer / rakshit

dumb people .... they have specified 1010 KVA ... which is
very high capacity.... high shear force exists if proper
rated engine is not coupled to generator ,,,, due to high
shear force.. wear in coupling.. wear in coupling... loose
studs... .. also greater vibrations is the cause

Is This Answer Correct ?    1 Yes 0 No

I have 1010 KVA Generator when i run the DG set for 5 to 6 hours the couplling (couplling joint in..

Answer / faisalabad

you may use self locking nut as well as suitable grate lock tight according bolts specfication

Is This Answer Correct ?    0 Yes 0 No

I have 1010 KVA Generator when i run the DG set for 5 to 6 hours the couplling (couplling joint in..

Answer / pavan

Use lock nuts. Because vibrations are unavoidable (but can
only be minimized), using lock nuts is always safe.

Is This Answer Correct ?    0 Yes 1 No

I have 1010 KVA Generator when i run the DG set for 5 to 6 hours the couplling (couplling joint in..

Answer / nagarajan

I Think u can make use of pins in the nuts at specified
tight point of bolt.

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Mechanical Engineering Interview Questions

What is sheet metal work?

0 Answers  


Explain the difference between the points of inflexion and contraflexure?

0 Answers  


what is p11

5 Answers  


How cavitation can be eliminated in a pump?

0 Answers  


What position do you prefer on a team working on a project?

2 Answers   Petro Star Mount,






Which turbine, high speed or low speed is efficient to generate 30MW power? or High RPM machine is more efficient or low RPM?

1 Answers   HMT,


conductivity of porous substance like sponge is depended or independent of pressure?

2 Answers  


How can I weld A234 WPB and WPB P11 fitting? Any special heat treatment required? What happen if I weld both?

0 Answers  


What are to be checked in an induction motor?

1 Answers   RRB,


what is the effect of steam turbine control valve throtting in turbine efficiency.

3 Answers  


What is a brake horse power?

1 Answers   RRB,


What causes damage to impellers?

3 Answers   RRB,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)