Answer / murthyvsn
Entry criteria should be fulfilled before system testing
begins
1.All the developed code must be unit tested.
2.All the s/w tools must be installed successfully and
functioning properly.
3.A separate QA environment must be available.
4.All the documents must be signedoff by business analyst.
Exit Criteria
1.Application must be having required resources.
2.All priority1 and priority2 bugs must be fixed
successfully.
3.Regression testing must be completed.
| Is This Answer Correct ? | 11 Yes | 0 No |
Entry and exit criteria is nothing but when to start
testing and when to stop testing.
Entry criteria:
All source codes are unit tested
All QA resource has enought functional knowledge
H/W and s/w are in place
Test plans and test cases are reviewed and signed off
Exit criteria:
Ensuring sufficient coverage of code
Ensuring sufficient coverage of functionality
Testing all of the high risk areas
The reliability of the product
The amount and severity of acceptable faults
The testing completeness deadline
| Is This Answer Correct ? | 10 Yes | 1 No |
Answer / palguna.akuleti
Entry criteria to one phase will become exit criteria to
other phase.
For suppose
Entry criteria :requirements for Design phase.
will come from First phase i.e information gathering phase.
Exit criteria :The out come from Design phase becomes Exit
criteria and becomes entry criteria for Coding phase.
if it is wrong please correct me.
| Is This Answer Correct ? | 11 Yes | 3 No |
Answer / hari
Entry criteria is nothingbut what to be needed for the
present testing and Exit criteria nothingbut what is the
ending of that testting
for example in system testing Entry criteria is
successfully compleetion of integration testing
Exit criteria are
Sign off system testing
one another example
for the Regression testing
Entry criteria : Testing of change requirements are signed
off
Exitcriteria: All regression test cases are executed
status Report document
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / murali
entry crteria means start the testing
exit criteria means stop the applicetion
| Is This Answer Correct ? | 2 Yes | 3 No |
Answer / bhasklar
Entry criteria is represent the entry testing,
exit criteria is represent the stop testing
| Is This Answer Correct ? | 0 Yes | 2 No |
Test cases for Internal IP Messenger
What is the mean by Test Management,Test Design,Test Execution,Test Plan,Test Specification?
can u explain me v-model?I told him we will do parallely both devolpment and testing . frs------------useraccepatance testing \ / srs system testing \ / HLD integration testing \ / LLD--------------------- unit testing \ / CODING he asked me how ur frs is done parallel with useracceptence testing and srs is done parallel to system testing and HLD IS done parallel to integration testing and LLD is done parallel to unit testing.Give me a clear clarification for it?
Tell me the test cases for Notepad?
What is Test Procedure? What are Test matrices? What is Tracibility matrix?
pls tell me who is in s/w testing field(either in company or as faculty) give the ans of my que. tel me why r u in testing ? reply me as soon as possible
At what stage of the life cycle does testing begin?
what is the challenging position faced in the testing not in point of management point of view it must be in the point of while testing the application?
What is Error Feeding?
Explain the ISO ( more information about the ISO)