Answer / vivek.gupta
Verification is done during the project planing and
development process. its a static testing and a part of QA.
Validation is done after the product(exe) build and its
dynamic testing and part of QC.
**:0)**
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / deepa
Verification invoives reviews and meetings to evaluate
documents,plans,code,requirements and specifications
Validation involves actual testing and takes place after
verifications are completes
| Is This Answer Correct ? | 0 Yes | 0 No |
Which methodology u follow in testcase?
what is call-pair ,cross testing,
I need a good book on manual testing.Is the book by nageswara rao good.I need to learn from basic to advanced.
what is the difference b/w test scenario and test case? pls explain with one example the preparation of both? thanks in advance ................
A general Question: If there are two bugs one with high priority and one with high severity, which bug should be fixed first?
What would be the designation of the tester in the company,would it be called as software engineer.
Hello Friends,I want some clearence regarding. Test report and Final report.
what is meant by port testing?
What is bug release notes? ....What does Bug release notes contain?
what is sevirity and who will decided that one?
11 Answers Creative Informatics, MBT, TCS,
what the tester should do ,if there are bugs in the requirements made by the business analyst?
How do you test if you have minimal or no documentation about the product?