The lowest level of the WBS is called what?
A. Code of accounts
B. Requirement
C. Milestone
D. Work package
No Answer is Posted For this Question
Be the First to Post Answer
You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75
You are the project manager for an outdoor concert event scheduled for 1 year from today. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You've decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll option for which contract type? A. Fixed price plus incentive B. Cost plus fixed fee C. Fixed price D. Cost plus incentive
What are the tools for process improvement?
During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing
How do you motivate team members?
You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project
Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14
Which of the following contracts should you use for projects that have a degree of uncertainty and require a large investment early in the project life cycle? A. Fixed price B. Cost reimbursable C. Lump sum D. Unit price
You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following? A. Technological advance B. Business need C. Customer request D. Legal requirement
You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time
If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.
You are in the Planning process of your project, and your project sponsor has requested an accurate cost estimate in two weeks from today. You'll use which of the following techniques to provide her with the most accurate cost estimate? A. Bottom-up B. Analogous C. Top-down D. Earned value