All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except?
A. Mitigation
B. Simulation
C. Avoidance
D. Acceptance


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process? A. Integrated Change Control B. Scope Change Control C. Schedule change control D. Cost change control

0 Answers  


You know that the next status meeting will require some discussion and a decision for a problem that has surfaced on the project. In order to make the most accurate decision, you know that the number of participants in the meeting should be limited to: A. 1 to 5 B. 5 to 11 C. 7 to 16 D. 10 to 18

0 Answers  


Lessons learned are used for all of the following except: A. To provide historical information that you can review during your next project B. To document employee performance C. To identify successes and failures on the project D. To record the causes of performance variances

0 Answers  


All of the following are tools and techniques of the Performance Reporting process except: A. Variance analysis B. Performance reporting C. Information distribution D. Performance reviews

0 Answers  


According to the Guide to the PMBOK, the project manager is identified and assigned during which process? A. As an input to the Initiation process B. As an input to the Planning process C. As an output of the Initiation process D. As an output of the Scope Planning process

0 Answers  






You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.

0 Answers  


Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating

0 Answers  


Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning

0 Answers  


Many times software delivery is late, why? Give reason.

0 Answers  


Performance reporting tools and techniques include all of the following except: A. Earned value analysis B. Statistical sampling C. Variance analysis D. Performance reviews

0 Answers  


You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A scope change has been requested. You know change is concerned with all of the following except: A. Managing change B. Verifying change C. Influencing causes of change D. Determining that a change occurred

0 Answers  


Which of the following processes are performed in the Closing process group and in what order? A. Administrative Closure then Contract Closeout B. Scope Verification then Administrative Closure C. Contract Closeout then Scope Verification D. Contract Closeout then Administrative Closure

0 Answers  


Categories