All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except?
A. Mitigation
B. Simulation
C. Avoidance
D. Acceptance


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

What is raid in project management?

0 Answers  


Which of the following is true regarding the staffing management plan needed for project activities? It is an output of the Resource Planning process. A. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Resource Planning process. B. It details how and when staff resources will be brought on and take off the project. It is an output of the Organizational Planning process. C. It details how and when staff resources wilt be brought on and take off the project. It is an output of the Resource Planning process. D. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Organizational Planning process.

0 Answers  


Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools

0 Answers  


Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques

0 Answers  


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

0 Answers  






If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

0 Answers  


You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.

0 Answers  


As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. This code refers to all of the following except: A. Reporting conflicts of interest B. Reporting experience and PMP status truthfully C. Complying with stakeholder requirements D. Complying with rules and policies of foreign countries

0 Answers  


You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A

0 Answers  


You are a project manager working on a new software product. Your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project? A. Budget B. Quality C. Time D. Schedule

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833

0 Answers  


Explain the Principals of Management

0 Answers   Mahatma Gandhi University,


Categories