Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except:
A. Personal integrity of others
B. Project management process
C. Personal integrity
D. Product integrity


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Each of the following is true regarding the risk management plan except: A. The risk management plan is an output of the Risk Management Planning process B. The risk management plan includes a description of the responses to risks and triggers. C. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets. D. The risk management plan is an input to all the remaining risk planning processes.

0 Answers  


What limits the options of the project team? A. Technology B. Constraints C. Deliverables D. Assumptions

0 Answers  


What are the csfs in the software project management ?

0 Answers  


You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.

0 Answers  


Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates

0 Answers  


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

0 Answers  


You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is over allocated. Which of the following is true? A. You should use resource requirements updates to determine availability and smooth out resource over allocation. B. You should use crashing to resource level the critical path tasks. C. You should use resource leveling heuristics to smooth out resource assignments. D. You should use fast tracking to resource level the critical path tasks.

1 Answers  


You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic

0 Answers  


Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates

0 Answers  


You are the project manager for Heart of Texas casual clothing company. Your project involves installing a new human resources system. You've identified the risks associated with this project and are ready for the next step. What is the next step? A. You will evaluate the risks and assign probabilities and impacts using Qualitative and/or Quantitative Risk Analysis. B. You will use the Delphi technique to confirm the risks you've detailed and identify others you may have missed. C. You must evaluate the risks and assign probabilities and impacts using both Qualitative Risk Analysis, which comes first, then Quantitative Risk Analysis. D. You will define the steps to take to respond to the risks and detail them in the risk response plan.

0 Answers  


What change would you like to bring in the management of your previous organization ?

0 Answers   EX,


All of the following are tools and techniques of the Performance Reporting process except: A. Variance analysis B. Performance reporting C. Information distribution D. Performance reviews

0 Answers  


Categories