Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


You are a project manager who has recently held a project team kickoff meeting where all the team members were formally introduced to each other. Some of the team members know each other from other projects and have been working with you for the past 3 weeks during the Planning processes. Which of the following is true?

A. Team building begins once all the members of the team are identified and introduced to each other. This team is in the storming stage of Team Development.
B. Team building begins at the Planning process. This team is in the storming stage of Team Development.
C. Team building begins once all the members of the team are identified and introduced to each other. This team is in the forming stage of Team Development.
D. Team building begins at the Planning process. This team is in the forming stage of Team Development.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating

0 Answers  


Your project has recently experienced change. Some of the agreed-upon WBS elements have been changed as a result. What kind of change has occurred? A. Schedule change B. Risk response change C. Quality change D. Scope change

0 Answers  


Describe the risk in software engineering.

0 Answers  


How do you handle conflicts in the Team Management ?

0 Answers   Microsoft,


Project managers spend what percentage of their prime communicating? A. 90 B. 85 C. 75 D. 50

0 Answers  


You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75

0 Answers  


You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of Scope Definition. You know if you don't correct this, one of the following could happen: A. The stakeholders will require overtime from the project team to keep the project on schedule. B. The WBS will adversely affect the deliverable breakdowns, and costs will increase. C. The scope management plan will require changes. D. The project costs could increase, there might be rework, and schedule delays may result.

0 Answers  


What are the five project management process groups, in order? A. Initiation, Executing, Planning, Controlling, and Closing B. Initiation, Controlling, Planning, Executing, and Closing C. Initiation, Planning, Controlling, Executing, and Closing D. Initiation, Planning, Executing, Controlling, and Closing

0 Answers  


You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time

0 Answers  


What is the key activity during Contract Closeout and Administrative Closure? A. Documenting lessons learned B. Creating project archives C. Disseminating information to formalize project closure D. Documenting project closure

0 Answers  


What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

0 Answers  


PERT is: A. The longest path B. A weighted average technique C. A simulation technique D. Widely used in practice to determine schedule durations

0 Answers  