You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope. Which of the following is true?
A. Project scope changes do not require CCB approval.
B. Performance measurement baselines are affected by scope changes.
C. Project scope change uses inspection to determine if change has occurred.
D. Project scope change uses workarounds to correct unexpected problems with scope change.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

The VP of marketing approaches you and requests that you change the visitor logon screen on the company’s website to include a username with at least six characters. This is considered: A. Project initiation B. Ongoing operations C. A project D. Project execution

1 Answers  


You are the project manager for your company's annual Spring Fling. You've made all the plans and reserved the outdoor grounds for the appropriate day and time. You are now two days away from the big day, and the forecast is calling for light rain showers in the afternoon. You rented tents just in case this risk occurred. This is an example of which Risk Response Planning tool and technique? A. Passive acceptance B. Contingency planning C. Avoidance D. Transference

0 Answers  


You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You are to add resources to the project. The sponsor agrees to pay the additional costs since time is now a critical factor. Which technique have you used? A. Crashing B. Resource leveling C. Fast tracking D. Resource loading

0 Answers  


You work for a company that writes hilling software programs for the communication industry. You've just been assigned a new project. The customer is located in a distant country that limits the number of foreigners allowed into the country. You identify this risk in your risk management plan. The critical point during the project is installation and setup. You might do which of the following given these circumstances? A. Use a design of experiments technique to develop a contingency plan. B. Develop a cause-and-effect diagram that identifies the contract type you should use for a project like this. C. Use sensitivity analysis to assist you in developing the appropriate risk response for this situation. D. Develop a contingency plan for installation.

0 Answers  


You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75

0 Answers  






You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic

0 Answers  


You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the scope statement and scope management plan for this project. In your interviews with some key stakeholders, you conclude which of the following? A. They understand that the scope statement assesses the Stability of the project scope and outlines how to incorporate scope changes into the project. B. They understand that the scope management plan assesses the stability of the project scope and outlines how to incorporate scope changes into the project. C. They understand that the scope management plan is deliverables oriented and cost estimates can be easily derived it. D. They understand that the scope statement is deliverables oriented and cost estimates can be easily derived from it.

0 Answers  


What are the tools and techniques of the Quantitative Risk Analysis process? A. Checklists, flowcharting, interviewing B. Interviewing, sensitivity analysis, decision tree analysis, simulation C. Checklists, sensitivity analysis, decision tree analysis, information-gathering techniques D. Interviewing, checklists, assumptions analysis, risk probability impact

0 Answers  


Performance reporting tools and techniques include all of the following except: A. Earned value analysis B. Statistical sampling C. Variance analysis D. Performance reviews

0 Answers  


You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You’re heading up a project to promote a new line of souvenirs to be sold at the shows. You need to gather the inputs to write the scope statement. You gather which of the following? A. Project charter, product description, assumptions, and constraints B. Project charter, product analysis, and cost benefit analysis C. Product description, product analysis, and project charter D. Product description, assumptions, constraints, and product analysis

0 Answers  


Explain the difference between Project management and IT management.

0 Answers   TCS,


The project manager has the greatest influence over quality during which process? A. Quality Planning B. Quality Assurance C. Quality Control D. Quality Change Control

0 Answers  


Categories