You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is over allocated. Which of the following is true?
A. You should use resource requirements updates to determine availability and smooth out resource over allocation.
B. You should use crashing to resource level the critical path tasks.
C. You should use resource leveling heuristics to smooth out resource assignments.
D. You should use fast tracking to resource level the critical path tasks.
Answer Posted / divya
answer is d
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What are the functions of project management tool?
Your company provides answering services for several major catalog retailers. The number of calls coming into the service center per month has continued to increase over the past 18 months. The phone system is approaching the maximum load limits and needs to be upgraded. You've been assigned to head up the upgrade project. Based on the company's experience with the vendor who worked on the last phone upgrade project, you're confident they'll be able to assist you with this project as well. Which of the following is true? A. You’ve made an assumption about vendor availability and expertise. The project came about due to a business need. B. Vendor availability and expertise are constraints. The project came about due to a business need. C. You've made an assumption about vendor availability and expertise. The project came about due to a marketing demand. D. Vendor availability and expertise are constraints. The project came about due to a marketing demand.
Many times software delivery is late, why? Give reason.
What type of organization experiences the least amount of stress during project closeout? A. Projectized B. Functional C. Weak matrix D. Strong matrix
The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals
You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true? A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process. B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process. C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process. D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.
You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the scope statement. This deliverable is a critical success factor. You should do which of the following? A. Inform the stakeholder that work not stated in the scope statement is excluded from the project. B. Modify the scope statement to reflect the new deliverable. C. Inform the stakeholder that this deliverable can be included in the next project since sign-off has already been obtained. D. Modify the scope statement after an approved change request has been received from the stakeholder.
The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project you're managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It's too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help speed up the project? A. Hire more resources to get the work completed faster. B. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources. C. Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement. D. Examine the project plan to see if there are any phases that can be fast tracked, and then revise the project plan to reflect the compression of the schedule.
During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing
All of the following are true regarding Ishikawa diagrams in the Quality Planning process except: A. They are also called cause-and-effect diagrams. B. They are also called fishbone diagrams. C. They are a tool and technique of this process. D. They are an output of this process.
You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time
You are a project manager for Snow Fun, a chain of retail shops specializing in winter sports gear and clothing. You’ve been working on contract with Snow Fun and are ready to move on to your next assignment. The customer has signed off on the project, formal acceptance notices have been distributed, and project closure procedures have been performed. What type of project ending is this? A. Extinction B. Starvation C. Integration D. Addition
Describe the 4 p’s in software project management.
You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You've been told that it is culturally unacceptable to eat certain foods in this country. You know that one of these foods happens to be a secret ingredient in the pizza sauce. What is the most appropriate response? A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it. B. Inform the potential partners that you suspect there might be a forbidden ingredient in the sauce and you'll request an investigation to determine if any of them exist in the sauce. C. Inform the potential partners that a forbidden ingredient exists in the sauce and determine to work with them to come up with another ingredient to replace that one. D. Don't tell the potential partners about the ingredient because the sauce they'll be using in the stores is shipped to them already prepared in cans. They won't know the ingredient is in the sauce.