You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of:
A. Crashing
B. Fast trucking
C. Resource leveling
D. Adjusting the resource calendar


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.

0 Answers  


How to deal with underperforming team members?

0 Answers  


You are a project manager for an international marketing firm. You are ready to assign resources to your new project using a work authorization system. All of the following are true except: A. Work authorization systems clarify and initiate the work for each work package. B. Work authorization systems are written procedures defined by the organization. C. Work authorization systems are tools and techniques of the Project Plan Execution process. D. Work authorization systems are an output of the Project Plan Execution process.

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  


What is "Readjustig goal and Milestone" in project managment and project planing

16 Answers   IBM,






What is the meaning of scope of the project?

0 Answers  


You are working on a project and are in the Quality Planning process. You know that if the customer requirements are not satisfied while the product is still in the control of the organization, it may result in corrective action, rework, scrapping, and downtime. Which of the following is true regarding the cost of quality? A. Cost of quality is an output of this process, and this is an internal failure cost. B. Cost of quality is a tool and technique of this process, and this is a prevention cost. C. Cost of quality is an output of this process, and this is a prevention cost. D. Cost of quality is a tool and technique of this process, and this is an internal failure cost.

0 Answers  


You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements

0 Answers  


The Project which is handled by you is in RED, customer has given you 4 weeks to show improvement, still nothing has worked out. The Customer again gives 3 weeks to improve and you do your best to improve, but nothing works out. Now the customer is not at all happy, HOW TO CONVINCE THIS CUSTOMER ???

8 Answers   AZS, BGR Energy, Wipro,


Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start

0 Answers  


You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written

0 Answers  


You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. You've been given a budget of $12 million to complete this project. Resources are easily attained. Which of the triple constraints is the primary constraint for this project? A. Time, because the date cannot be moved B. Money, because the budget is set at $12 million C. Resources, because they're not fixed D. Quality, because the buildings have to be functional and safe

0 Answers  


Categories