An IS auditor is reviewing a project that is using an agile software development approach. Which of the following should the IS auditor expect to find?
A. Use of a capability maturity model (CMM)
B. Regular monitoring of task-level progress against schedule
C. Extensive use of software development tools to maximize team productivity
D. Postiteration reviews that identify lessons learned for future use in the project
the answer is D.
A. The capability maturity model (CMM) places heavy emphasis on predefined formal processes and formal project management and software development deliverables, while agile software development projects, by contrast, rely on refinement of process as dictated by the particular needs of the project and team dynamics.
B. Task-level tracking is not used because daily meetings identify challenges and impediments to the project.
C. Agile projects make use of suitable development tools; however, tools are not seen as the primary means of achieving productivity. Team harmony, effective communications and collective ability to solve challenges are of greater importance.
D. A key tenet of the agile approach to software project management is ongoing team learning to refine project management and software development processes as the project progresses. One of the best ways to achieve this is that the team considers and documents what worked well and what could have worked better at the end of each iteration and identifies improvements to be implemented in subsequent iterations. Additionally, less importance is placed on formal paper-based deliverables, with the preference being effective informal communication within the team and with key outside contributors. Agile projects produce releasable software in short iterations, typically ranging from four to eight weeks. This, in itself, instills considerable performance discipline within the team. This, combined with short daily meetings to agree on what the team is doing and the identification of any impediments, renders task-level tracking against a schedule redundant.
Question #: 424 CISA Job Practice Task Statement: 3.5
Is This Answer Correct ? | 5 Yes | 0 No |
The PRIMARY reason for using digital signatures is to ensure data: A. confidentiality. B. integrity. C. availability. D. timeliness.
Change management procedures are established by IS management to: A. control the movement of applications from the test environment to the production environment. B. control the interruption of business operations from lack of attention to unresolved problems. C. ensure the uninterrupted operation of the business in the event of a disaster. D. verify that system changes are properly documented.
Facilitating telecommunications continuity by providing redundant combinations of local carrier T-1 lines, microwaves and/or coaxial cables to access the local communication loop is: A. last mile circuit protection. B. long haul network diversity. C. diverse routing. D. alternative routing.
In which of the following network configurations would problem resolution be the easiest? A. Bus B. Ring C.Star D. Mesh
Which of the following is a control over component communication failure/errors? A. Restricting operator access and maintaining audit trails B. Monitoring and reviewing system engineering activity C. Providing network redundancy D. Establishing physical barriers to the data transmitted over the network
A digital signature contains a message digest to: A. show if the message has been altered after transmission. B. define the encryption algorithm. C. confirm the identity of the originator. D. enable message transmission in a digital format.
Which of the following is widely accepted as one of the critical components in networking management? A. Configuration management B. Topological mappings C. Application of monitoring tools D. Proxy server trouble shooting
Which of the following tests is an IS auditor performing when a sample of programs is selected to determine if the source and object versions are the same? A. A substantive test of program library controls B. A compliance test of program library controls C. A compliance test of the program compiler controls D. A substantive test of the program compiler controls
Which of the following statements relating to packet switching networks is CORRECT? A. Packets for a given message travel the same route. B. Passwords cannot be embedded within the packet. C. Packet lengths are variable and each packet contains the same amount of information. D. The cost charged for transmission is based on packet, not distance or route traveled.
1 Answers Karura Community Chapel,
An IS auditor evaluates the test results of a modification to a system that deals with payment computation. The auditor finds that 50 percent of the calculations do not match predetermined totals. Which of the following would MOST likely be the next step in the audit? A. Design further tests of the calculations that are in error. B. Identify variables that may have caused the test results to be inaccurate. C. Examine some of the test cases to confirm the results. D. Document the results and prepare a report of findings, conclusions and recommendations.
Which of the following BEST determines that complete encryption and authentication protocols exist for protecting information while transmitted? A. A digital signature with RSA has been implemented. B. Work is being done in tunnel mode with the nested services of AH and ESP C. Digital certificates with RSA are being used. D. Work is being done in transport mode, with the nested services of AH and ESP
An organization has an integrated development environment (IDE), where the program libraries reside on the server, but modification/development and testing are done from PC workstations. Which of the following would be a strength of an integrated development environment? A. Controls the proliferation of multiple versions of programs B. Expands the programming resources and aids available C. Increases program and processing integrity D. Prevents valid changes from being overwritten by other changes