Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


10'0" × 10'0" Proposed room Start and Finish How many Cement & Sand & Bricks & Metals & Steels Need



10'0" × 10'0" Proposed room Start and Finish How many Cement & Sand &a..

Answer / anil

10'x10'=100sqft,i.e=100/10.76=9.29m2,Brick work width=150mm or 6'',then,volume of brick work=9.29x0.15=1.39m3.
size of brick=9''x4''x6'' or 230mm x100mm x 150 mm,add morter 12mm,then size of brick =242x112x150mm=0.0041m3,so calculate the nos of bricks=1.39/0.0041=340Nos of bricks

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

Why steel rods are produced only in even dimensions?

0 Answers   Billimoria,


what is ment by water cement ratio

2 Answers   CSIR, GIPL, Madhucon, NBCC, TCS,


How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?

0 Answers   Aircel,


How to calculate the design of column by simple method? 

2 Answers   L&T,


how to find fineness modulus of sand?

3 Answers  


What are your future hopes for this job?

0 Answers   Jaycon,


clear cover means the distance between main bar outer face to shuttering face. Is it right?

4 Answers  


what are the changes in concrete pour height as per IS 456, 2009?

0 Answers  


what is development length,where it is used and why it is used?

1 Answers  


Kindly tell me how much extra steel bars are provided in a RCC roof and distance of bends in different sizes of roofs. Please also tell me that bars provided in chajja are taken seperate or main bars or short bars are extended in chajja. please send me the answer@ suhail_akhter@hotmail.com

2 Answers  


Wat is the optimum value of tensile strength of concrete after 28 days??

1 Answers  


In pile foundation which kind of action are take place?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)