How much sand for a 107sqm residensial building
Answer / jaswinder singh kalsi
sand for 107 sqm building??
VOLUME OF CONCRETE REQUIRED= 107*0.127(SLAB THICKNESS)=13.589 CU.M
consider M15 GRADE OF CONCRETE ( 1:2:4)
1CU.M WET CONCRETE =1.54 CU.M DRY CONCRETE
QUANTITY OF CEMENT= 1.54*13.589/7 =2.98 CU.M
QUANTITY OF SAND = 2*2.98=5.97CU.M
Is This Answer Correct ? | 20 Yes | 4 No |
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
How much overlapping required for welding the reinforcement bars in Columns & beams
How To do Steel Design of Beam,Columm,Slab,Staircase,Wall?
Whats the size cube
2 Answers Shimla Hills Construction,
what is studds? where it can be done?
what is meant by point of contraflexure?
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
types of concrete?
What is the lap lenth for welded joints for reinforcement bars. and what is its IS code no.
in railway engineering, what are the types of guages? what is its size,length & thickness?
what happened if the diameter of capillary tube is double then the capillary rise will be
Can we use concrete of slump cone in cube casting in which we have already measured slump?