what is the difference between lap length & development
length of reinforcement steel
bars
Answer / biv05
lapping is provided when the main steel is generally not enough for the span I.e more than 12 m r/f is provided
for 8 mm -400mm
10mm-500mm
12mm-600mm
16mm-800mm
20-1200mm
DEVELOPMENT LENGTH: is the length of the vertical steel generally taken as a L shape ..this length is critical as compression is higher on this point ..
formule: l*d 10d
| Is This Answer Correct ? | 3 Yes | 0 No |
what will happen if we use milk or oil in the place of water in concrete??????????
how to calculate the steel for 450 sft slab, please tell me the solution method
in 1:4,1:6 and 1:8 cement mortar mix how much water required? and find water cement ratio?
how much volume is one bag cement of 50kg
15 Answers Portland, RJB, UltraTech,
how many cement and sand required for 1m2 plastering 1:4 cm
is their any instrument which can detect steel after casting of slab,etc. for verification of steel in slab,etc.
what will be the grade for M 30 ,35,40,45,50,55???
How do you find the difference between 53&43 grade cement in site?
Which IS code is used for scrap of reinforcement steel?
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
Which are the Steel tests ?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)