According to my experience the most challenging situation with developers is when the bugs you have produced are not producible over their environment . The It will be difficult to covey the exact bug . It becomes more difficult when the T and D are in different geographical region . But you can overcome this by right way of communication .
Sometime you will find a mismatch between T and D when the priority and severity of the Bug comes into account . But it can also be resolver with proper guidance .
| Is This Answer Correct ? | 0 Yes | 0 No |
How do you start a project plan?
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
Name the ethical code you'll be required to adhere to as a PMP. A. Project Management Policy and Ethics Guide B. Project Management Professional Standards and Ethics C. Project Management Code of Professional Ethics D. Project Management Professional Code of Professional Conduct
You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150
What is the concept of project management?
You are a project manager and are in the Closing process of the project. Your customer has been presented with a formal acceptance and sign-off document. They refuse to sign, claiming the product does not meet their expectations. You know that this situation could have been prevented by doing all of the following except : A. Documenting the requirements B. Documenting the customer's refusal to sign C. Performing quality inspections during the process D. Requesting sign-off at important milestones
You are a project manager for Cashiers Systems. Your company produces cashiering systems and software for the retail industry. Your customer has requested a change that will change the characteristics of the cashiering system. You've described the characteristics of the cashiering system using this tool and technique of the Integrated Change Control process: A. Product description B. Product analysis C. Decomposition D. Configuration management
You are working on a project to develop a new website for your company. You are monitoring results of the project to determine if they comply with standards set out during the Planning processes. You are also taking steps to eliminate unsatisfactory results. This might mean rework in some cases. Which process are you in? A. Risk Monitoring and Control B. Quality Control C. Integrated Change Control E. Scope Change Control
The project manager, stakeholders, and project team members all have roles and responsibilities throughout the project. As the project manager, you might link the project scope definition to the project roles and indicate which activities each person will participate in. You might display this information in which of the following ways: A. PDM B. RAM C. SOW D. RRM
The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures
Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.
You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time