Diagonal check is required for a layout work to confirm ––
Answers were Sorted based on User's Feedback
Answer / k c kumar
To confirm the dimension of the member generally Columns.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / sjtbehera
yes it is to conform the dimension of the respective
structure and distance.
| Is This Answer Correct ? | 1 Yes | 0 No |
What is called dummy column, & what its uses ?
What are the common ways of demolition?
What is the difference between linear dimension and aligned dimension?
How many mortar required for Brickwork of 1 Cu.m works??
how many m3, mason should done per day if he going to build 4.5 inch brick work(partition wall)?
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
in 100 cft = 1350 bricks in 100 cft = ? bloks
List out some of the common problems that architect have to tackle it?
what are the types of design? which type of method is used at what type of design & why?
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
19 Answers DNA Infrastructure, HCC, L&T,
What is the amount of brick in cum we get in a BIG LORRY approx ??
What is critical path method (c.p.m)?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)