If the on Of the DO module is off in the System cabinet,
then what is the Procedure to check weather the Module is
working or not.

Answers were Sorted based on User's Feedback



If the on Of the DO module is off in the System cabinet, then what is the Procedure to check weathe..

Answer / a k gunjariya

If DO Module is OFF in system cabinets:
1.) Check status of the 24 V Power Supply (power supply LED
on the module)
2.) IF No LED is glowing then module is not getting power
supply.
3.) if power supply led is glowing then check any of the
Digital Output signal by simulating input.

Is This Answer Correct ?    10 Yes 0 No

If the on Of the DO module is off in the System cabinet, then what is the Procedure to check weathe..

Answer / ahmed samy

Make forcing from PLC programming software to any output Channel in that DO, if output is on, LED is on means module is ok, otherwise it's faulty.

Other idea, is to replace module with similar one in the rack, if it's still off in second position that means it has a problem

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Instrumentation Interview Questions

why we cant transmit the dc current easily

1 Answers  


Why we use DPT? can we use PT instead of DPT?

2 Answers  


what is Mv with respect to temprature in thermocouple

2 Answers  


Why we are using 4-20 mA as Analog signal transmission other than 3 to 19 or 2 to 18 or 6 to 22 like wise ? What is the reason behind using 4 & 20 mA? Can anyone give proper technical reply ?

5 Answers   Air Liquide,


Identify and use the ANSI/ISA-S5.1 consensus industrial standard process symbols.

0 Answers   GAIL, Olympia,






What is BMS (Building Managment System)& is AHU / HVAC are in BMS.

12 Answers   Alghanim,


what is the difference between transmitter and converters?

9 Answers   Videocon,


what is buoyancy law?

1 Answers  


what's the minimum level required of SIL (safety integrity level)to use fire and gas system?

2 Answers   L&T,


tell me about Woodward505 Function as a point of Instrument Engineer.

4 Answers  


May I have a brief note above the voltage barriers? Whats is the purpose? Please mail me if you've operational details, mail id: rajkumar.diice@gmail.com

0 Answers  


What care will you take in the installation of control valves,SCADA,DCS and FOC in Oil and Gas Project?

0 Answers   KNPC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)