is there any difference in reading or error in value, if we
connect the R phase in Y terminal and Y phase in R terminal
of electronic energy meter of 11 kv feerders???
Answer / k.prakashchandra
No. But corresponding CTs and PTs should not be
altered.Please note that the R, Y, B phases of one station
may be different from those of another station.In case of 11
KV, only phase sequence is considered. Energy recorded by
energy meter is the sum of individual measuring elements..
| Is This Answer Correct ? | 2 Yes | 0 No |
what is the function of commutator in dc motor?
during parallel operation of two ac generator which condition must match before taking both parallel i.e speed /voltage rating /kva/exciation
What is self exciting?
If two Transformers are connected in parallel having impedance of 50KA in both transformers will the impedance increase or decrease after connecting transformers in parallel?
what is formula of dc current and resistance.
What is speed mode?
what is model question rrb junior engineer electrical gr.II
we have two motors 1250kW,6.6kV to be coupled on the same shaft ,so please provide assistance for their synchronisation.
i installed 100kva ups. what KVA genset they should provid in input side? plz any update formula or ans with reason.
What is reactance, reluctance,capistance, pls give answeer in hinglish and be simply Jo asani we smajh m aa jaye
WHAT IS THE DIFFERENCE BETWEEN AN ACB & mccb 7 WHAT IS THE CRITERIA WHEN TO USE WHICH OF THE TWO
How we Use DC Power in Transformers? is it possible ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)