in a power plant main steam flow is volumetric or mass flow?
is it required compensation?
Answer / bablu choudhary
If, we use LPT and HPT used for full STIG ,then volumetric flow rates of the turbine is to be constant to maintain the pressure ratio of gas turbine while the mass flow rates of the STIG is lower than that of gas turbine.
so compensation is not required in case of mass flow rate it only allow to flows the volumetric flow rate.
THANKS.
| Is This Answer Correct ? | 1 Yes | 0 No |
Where we cant instal mass flow meter.
In turbine what does term CDP, NI, NH, HSSOC means.
in instrumentation why we are using 4-20mA , why not voltage ? if somebody design a instrument which works on voltage then can we use that instrument?
What is Modbus communication
Q- Why Phase tester is only used for checking AC not DC ?
while i check zero check for dp flow transmitter some fluctuating came (0 to 458 kg/h) what is the reason?
Boolean algebra
What is the difference between Error and Offset.
If the Barrier Fails during online then What will be the control valve position in field or Positioner action in the field.
How does a redundant controller comes in line when the main controller fails??
We have yokogawa cs3000 one fcs and 4 his. After download to his, showing successfully at es, but not transferred to his.
what is insdustrial vibration.who it works. give atleast 2 types of insdustrial vibration
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)