A vendor/contractor?s performance against service level
agreements must be evaluated by the:
A. customer.
B. contractor.
C. third-party.
D. contractor?s management.
Answer / guest
Answer: A
Only the customer should evaluate the supplier?s performance
in a service level agreement (SLA). This makes the customer
confident of the service provided by the supplier. However,
the decision of what to measure must be decided by the
customer and the supplier.
Is This Answer Correct ? | 5 Yes | 0 No |
Which of the following disaster recovery/continuity plan components provides the GREATEST assurance of recovery after a disaster? A. The alternate facility will be available until the original information processing facility is restored. B. User management was involved in the identification of critical systems and their associated critical recovery times. C. Copies of the plan are kept at the homes of key decision making personnel. D. Feedback to management assuring them that the business continuity plans are indeed workable and that the procedures are current.
The database administrator has recently informed you of the decision to disable certain normalization controls in the database management system (DBMS) software to provide users with increased query performance. This will MOST likely increase the risk of: A. loss of audit trails. B. redundancy of data. C. loss of data integrity. D. unauthorized access to data.
A company has recently upgraded its purchase system to incorporate EDI transmissions. Which of the following controls should be implemented in the EDI interface in order to provide for efficient data mapping? A. Key verification B. One-for-one checking C. Manual recalculations D. Functional acknowledgements
IT governance ensures that an organization aligns its IT strategy with: A. Enterprise objectives. B. IT objectives. C. Audit objectives. D. Finance objectives.
Compensating controls are intended to: A. reduce the risk of an existing or potential control weakness. B. predict potential problems before they occur. C. remedy problems discovered by detective controls. D. report errors or omissions.
Which of the following is the MOST important criterion for the selection of a location for an offsite storage facility for IS backup files? The offsite facility must be: A. physically separated from the data center and not subject to the same risks. B. given the same level of protection as that of the computer data center. C. outsourced to a reliable third party. D. equipped with surveillance capabilities.
An organization having a number of offices across a wide geographical area has developed a disaster recovery plan (DRP). Using actual resources, which of the following is the MOST cost-effective test of the DRP? A. Full operational test B. Preparedness test C. Paper test D. Regression test
The impact of EDI on internal controls will be: A. that fewer opportunities for review and authorization will exist. B. an inherent authentication. C. a proper distribution of EDI transactions while in the possession of third parties. D. that IPF management will have increased responsibilities over data center controls.
An IS auditor evaluates the test results of a modification to a system that deals with payment computation. The auditor finds that 50 percent of the calculations do not match predetermined totals. Which of the following would MOST likely be the next step in the audit? A. Design further tests of the calculations that are in error. B. Identify variables that may have caused the test results to be inaccurate. C. Examine some of the test cases to confirm the results. D. Document the results and prepare a report of findings, conclusions and recommendations.
purchase orders issued to vendors have been authorized as per the authorization matrix
Which of the following would contribute MOST to an effective business continuity plan (BCP)? The BCP: A. document was circulated to all interested parties. B. planning involved all user departments. C. was approved by senior management. D. was audited by an external IS auditor.
An IS auditor is reviewing the risk management process. Which of the following is the MOST important consideration during this review? A. Controls are implemented based on cost-benefit analysis. B. The risk management framework is based on global standards. C. The approval process for risk response is in place. D. IT risk is presented in business terms.