Which of the following group/individuals should assume
overall direction and responsibility for costs and
timetables of system development projects?

A. User management

B. Project steering committee

C. Senior management

D. Systems development management



Which of the following group/individuals should assume overall direction and responsibility for cos..

Answer / guest

Answer: B

The project steering committee is ultimately responsible for
all costs and timetables. User management assumes ownership
of the project and the resulting system. Senior management
commits to the project and approves the resources necessary
to complete the project. System development management
provides technical support for the hardware and software
environments by developing, installing and operating the
requested system.

Is This Answer Correct ?    9 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

Separation of duties between computer opeartors and other data processing personnel is intended to: A. Prevent unauthorized modifications to program or data. B. Reduce overall cost of operations C. Allow operators to concentrate on their assigned duties D. Restrict operator access to data

2 Answers  


An IS auditor reviewing database controls discovered that changes to the database during normal working hours were handled through a standard set of procedures. However, changes made after normal hours required only an abbreviated number of steps. In this situation, which of the following would be considered an adequate set of compensating controls? A. Allow changes to be made only with the DBA user account. B. Make changes to the database after granting access to a normal user account C. Use the DBA user account to make changes, log the changes and review the change log the following day. D. Use the normal user account to make changes, log the changes and review the change log the following day.

1 Answers  


Which of the following provides the GREATEST assurance of message authenticity? A. The pre-hash code is derived mathematically from the message being sent. B. The pre-hash code is encrypted using the sender's private key. C. Encryption of the pre-hash code and the message using the secret key. D. Sender attains the recipient's public key and verifies the authenticity of its digital certificate with a certificate authority.

1 Answers  


A number of system failures are occurring when corrections to previously detected errors are resubmitted for acceptance testing. This would indicate that the maintenance team is probably not adequately performing which of the following types of testing? A. Unit testing B. Integration testing C. Design walk-throughs D. Configuration management

1 Answers  


Which of the following would be included in an IS strategic plan? A. Specifications for planned hardware purchases B. Analysis of future business objectives C. Target dates for development projects D. Annual budgetary targets for the IS department

2 Answers  






As part of the business continuity planning process, which of the following should be identified FIRST in the business impact analysis (BIA)? A. Organizational risks, such as single point-of-failure and infrastructure risk B. Threats to critical business processes C. Critical business processes for ascertaining the priority for recovery D. Resources required for resumption of business

1 Answers  


A utility is available to update critical tables in case of data inconsistency. This utility can be executed at the OS prompt or as one of menu options in an application. The BEST control to mitigate the risk of unauthorized manipulation of data is to: A. delete the utility software and install it as and when required. B. provide access to utility on a need-to-use basis. C. provide access to utility to user management D. define access so that the utility can be only executed in menu option.

2 Answers  


Which of the following is widely accepted as one of the critical components in networking management? A. Configuration management B. Topological mappings C. Application of monitoring tools D. Proxy server trouble shooting

1 Answers  


A universal serial bus (USB) port: A. connects the network without a network card. B. connects the network with an Ethernet adapter. C. replaces all existing connections. D. connects the monitor.

1 Answers  


Which of the following groups should assume ownership of a systems development project and the resulting system? A. User management B. Senior management C. Project steering committee D. Systems development management

3 Answers  


Which of the following is a control to detect an unauthorized change in a production environment? A. Denying programmers access to production data. B. Requiring change request to include benefits and costs. C. Periodically comparing control and current object and source programs. D. Establishing procedures for emergency changes.

1 Answers  


Disaster recovery planning addresses the: A. technological aspect of business continuity planning. B. operational piece of business continuity planning. C. functional aspect of business continuity planning. D. overall coordination of business continuity planning.

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)