In regard to moving an application program from the test
environment to the production environment, the BEST control
would be provided by having the:

A. application programmer copy the source program and
compiled object module to the production libraries.

B. as paul says,

C. production control group compile the object module to the
production libraries using the source program in the test
environment.

D. production control group copy the source program to the
production libraries and then compile the program.



In regard to moving an application program from the test environment to the production environment,..

Answer / guest

Answer: D

The best control would be provided by having the production
control group copy the source program to the production
libraries and then compile the program.

Is This Answer Correct ?    5 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

Which of the following audit procedures would MOST likely be used in an audit of a systems development project? A. Develop test transactions B. Use code comparison utilities C. Develop audit software programs D. Review functional requirements documentation

1 Answers  


An IS auditor recommends that an initial validation control be programmed into a credit card transaction capture application. The initial validation process would MOST likely: A. check to ensure the type of transaction is valid for that card type. B. verify the format of the number entered then locate it on the database. C. ensure that the transaction entered is within the cardholder's credit limit. D. confirm that the card is not shown as lost or stolen on the master file.

1 Answers  


An IS auditor performing a review of the IS department discovers that formal project approval procedures do not exist. In the absence of these procedures the IS manager has been arbitrarily approving projects that can be completed in a short duration and referring other more complicated projects to higher levels of management for approval. The IS auditor should recommend as a FIRST course of action that: A. users participate in the review and approval process. B. formal approval procedures be adopted and documented. C. projects be referred to appropriate levels of management for approval. D. the IS manager's job description be changed to include approval authority.

2 Answers  


An organization acquiring other businesses continues using its legacy EDI systems, and uses three separate value added network (VAN) providers. No written VAN agreements exist. The IS auditor should recommend that management: A. obtain independent assurance of the third party service providers. B. set up a process for monitoring the service delivery of the third party. C. ensure that formal contracts are in place. D. consider agreements with third party service providers in the development of continuity plans.

1 Answers  


An IS auditor who is participating in a systems development project should: A. recommend appropriate control mechanisms regardless of cost. B. obtain and read project team meeting minutes to determine the status of the project. C. ensure that adequate and complete documentation exists for all project phases. D. not worry about his/her own ability to meet target dates since work will progress regardless.

1 Answers  






An IS auditor reviewing back-up procedures for software need only determine that: A. object code libraries are backed up. B. source code libraries are backed up. C. both object and source codes libraries are backed up. D. program patches are maintained at the originating site.

1 Answers  


An IS auditor reviewing an organization's IS disaster recovery plan should verify that it is: A. tested every 6 months. B. regularly reviewed and updated. C. approved by the chief executive officer (CEO). D. communicated to every departmental head in the organization.

2 Answers  


Many IT projects experience problems because the development time and/or resource requirements are underestimated. Which of the following techniques would provide the GREATEST assistance in developing an estimate of project duration? A. Function point analysis B. PERT chart C. Rapid application development D. Object-oriented system development

1 Answers  


The MOST effective method of preventing unauthorized use of data files is: A. automated file entry. B. tape librarian. C. access control software. D. locked library.

1 Answers  


In a TCP/IP-based network, an IP address specifies a: A. network connection. B. router/gateway. C. computer in the network. D. device on the network.

1 Answers  


Which of the following is an implementation risk within the process of decision support systems? A. Management control B. Semistructured dimensions C. Inability to specify purpose and usage patterns D. Changes in decision processes

1 Answers  


An independent software program that connects two otherwise separate applications sharing computing resources across heterogeneous technologies is known as: A. middleware. B. firmware. C. application software. D. embedded systems.

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)