Many IT projects experience problems because the development
time and/or resource requirements are underestimated. Which
of the following techniques would provide the GREATEST
assistance in developing an estimate of project duration?

A. Function point analysis

B. PERT chart

C. Rapid application development

D. Object-oriented system development



Many IT projects experience problems because the development time and/or resource requirements are ..

Answer / guest

Answer: B

Function point analysis is a technique for determining the
size of a development task based on the number of function
points. Function points are factors such as inputs, outputs,
inquiries, logical internal file, etc. While this will help
determine the size of individual activities, it will not
assist in determining project duration since there are many
over-lapping tasks. A PERT chart will help determine project
duration once all the activities and the work involved in
the activities are known. Rapid application development is a
methodology that enables organizations to develop
strategically important systems faster while reducing
development costs and maintaining quality, and
object-oriented system development is the process of
solution specification and modeling.

Is This Answer Correct ?    5 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

In which of the following network configurations would problem resolution be the easiest? A. Bus B. Ring C.Star D. Mesh

1 Answers  


When auditing a mainframe operating system, what would the IS auditor do to establish which control features are in operation? A. Examine the parameters used when the system was generated B. Discuss system parameter options with the vendor C. Evaluate the systems documentation and installation guide D. Consult the systems programmers

1 Answers  


Functionality is a characteristic associated with evaluating the quality of software products throughout their lifecycle, and is BEST described as the set of attributes that bear on the: A. existence of a set of functions and their specified properties. B. ability of the software to be transferred from one environment to another. C. capability of software to maintain its level of performance under stated conditions. D. relationship between the performance of the software and the amount of resources used.

1 Answers  


Large-scale systems development efforts: A. are not affected by the use of prototyping tools. B. can be carried out independent of other organizational practices. C. require that business requirements be defined before the project begins. D. require that project phases and deliverables be defined during the duration of the project.

1 Answers  


Which of the following BEST describes the role of a systems analyst? A. Defines corporate databases B. Designs systems based on the needs of the user C. Schedules computer resources D. Tests and evaluates programmer and optimization tools

1 Answers  






When reviewing a business process reengineering (BPR) project, which of the following is the MOST important for an IS auditor to evaluate? A. The impact of removed controls. B. The cost of new controls. C. The BPR project plans. D. The continuous improvement and monitoring plans.

1 Answers  


Which of the following would be of MOST concern to an IS auditor reviewing a VPN implementation? Computers on the network that are located: A. on the enterprise's facilities. B. at the backup site. C. in employees' homes. D. at the enterprise's remote offices.

1 Answers  


Losses can be minimized MOST effectively by using outside storage facilities to do which of the following? A. Provide current, critical information in backup files B. Ensure that current documentation is maintained at the backup facility C. Test backup hardware D. Train personnel in backup procedures

1 Answers  


A long-term IS employee with a strong technical background and broad managerial experience has applied for a vacant position in the IS audit department. Determining whether to hire this individual for this position should be based on the individual's experience and: A. the length of service since this will help ensure technical competence. B. age as training in audit techniques may be impractical. C. IS knowledge since this will bring enhanced credibility to the audit function. D. ability, as an IS auditor, to be independent of existing IS relationships.

2 Answers  


Which of the following controls would be MOST effective in ensuring that production source code and object code are synchronized? A. Release-to-release source and object comparison reports B. Library control software restricting changes to source code C. Restricted access to source code and object code D. Date and time-stamp reviews of source and object code

2 Answers  


LANs: A. protect against virus infection. B. protect against improper disclosure of data. C. provide program integrity from unauthorized changes. D. provide central storage for a group of users.

1 Answers  


Data flow diagrams are used by IS auditors to: A. order data hierarchically. B. highlight high-level data definitions. C. graphically summarize data paths and storage. D. portray step-by-step details of data generation.

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)