Many IT projects experience problems because the development
time and/or resource requirements are underestimated. Which
of the following techniques would provide the GREATEST
assistance in developing an estimate of project duration?

A. Function point analysis

B. PERT chart

C. Rapid application development

D. Object-oriented system development

Answer Posted / guest

Answer: B

Function point analysis is a technique for determining the
size of a development task based on the number of function
points. Function points are factors such as inputs, outputs,
inquiries, logical internal file, etc. While this will help
determine the size of individual activities, it will not
assist in determining project duration since there are many
over-lapping tasks. A PERT chart will help determine project
duration once all the activities and the work involved in
the activities are known. Rapid application development is a
methodology that enables organizations to develop
strategically important systems faster while reducing
development costs and maintaining quality, and
object-oriented system development is the process of
solution specification and modeling.

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2838


purchase orders issued to vendors have been authorized as per the authorization matrix

1089