The use of a GANTT chart can:
A. aid in scheduling project tasks.
B. determine project checkpoints.
C. ensure documentation standards.
D. direct the post-implementation review.
Answers were Sorted based on User's Feedback
Answer / guest
Answer: A
A GANTT chart is used in project control. It may aid in the
identification of needed checkpoints but its primary use is
in scheduling. It will not ensure the completion of
documentation nor will it provide direction for the
post-implementation review.
| Is This Answer Correct ? | 10 Yes | 0 No |
Transmitting redundant information with each character or frame to facilitate detection and correction of errors is called: A. feedback error control. B. block sum check. C. forward error control. D. cyclic redundancy check.
Which of the following is the BEST way to handle obsolete magnetic tapes before disposing of them? A. Overwriting the tapes B. Initializing the tape labels C. Degaussing the tapes D. Erasing the tapes
Which of the following data validation edits is effective in detecting transposition and transcription errors? A. Range check B. Check digit C. Validity check D. Duplicate check
In the development of an important application affecting the entire organization, which of the following would be the MOST appropriate project sponsor? A. The information systems manager B. A member of executive management C. An independent management consultant D. The manager of the key user department
An IS auditor has recently discovered that because of a shortage of skilled operations personnel, the security administrator has agreed to work one late-night shift a month as the senior computer operator. The MOST appropriate course of action for the IS auditor is to: A. advise senior management of the risk involved. B. agree to work with the security officer on these shifts as a form of preventative control. C. develop a computer-assisted audit technique to detect instances of abuses of this arrangement. D. review the system log for each of the late-night shifts to determine whether any irregular actions occurred.
Passwords should be: A. assigned by the security administrator. B. changed every 30 days at the discretion of the user. C. reused often to ensure the user does not forget the password. D. displayed on the screen so that the user can ensure that it has been entered properly.
An IS auditor performing a telecommunication access control review should be concerned PRIMARILY with the: A. maintenance of access logs of usage of various system resources. B. authorization and authentication of the user prior to granting access to system resources. C. adequate protection of stored data on servers by encryption or other means. D. accountability system and the ability to identify any terminal accessing system resources.
Which of the following concerns associated with the World Wide Web would be addressed by a firewall? A. Unauthorized access from outside the organization B. Unauthorized access from within the organization C. A delay in Internet connectivity D. A delay in downloading using file transfer protocol (FTP)
In a risk-based audit approach an IS auditor should FIRST complete a/an: A. inherent risk assessment. B. control risk assessment. C. test of control assessment. D. substantive test assessment.
A disaster recovery plan (DRP) for an organization should: A. reduce the length of the recovery time and the cost of recovery. B. increase the length of the recovery time and the cost of recovery. C. reduce the duration of the recovery time and increase the cost of recovery. D. not affect the recovery time nor the cost of recovery.
After installing a network, an organization installed a vulnerability assessment tool or security scanner to identify possible weaknesses. Which is the MOST serious risk associated with such tools? A. Differential reporting B. False positive reporting C. False negative reporting D. Less detail reporting
During an IT audit of a large bank, an IS auditor observes that no formal risk assessment exercise has been carried out for the various business applications to arrive at their relative importance and recovery time requirements. The risk that the bank is exposed to is that the: A. business continuity plan may not have been calibrated to the relative risk that disruption of each application poses to the organization. B. business continuity plan may not include all relevant applications and therefore may lack completeness in terms of its coverage. C. business impact of a disaster may not have been accurately understood by the management. D. business continuity plan may lack an effective ownership by the business owners of such applications.