Software Quality Assurance
Progress:

Scenario
I. Defining SQA milestones
II. Assigning SQA resources
III. SQA scheduling
IV. SQA budgeting
V. Selecting software development tools that will
interface with the SQA tools
VI. Reviewing any contracts with subcontractors for SQA
requirements
In the above statements, which of the tasks are included
in planning the overall SQA effort?
Choice 1
I, III, V, and VI
Choice 2
I, II, III, and IV
Choice 3
I, II, III, and V
Choice 4
III, IV, V, and VI
Choice 5
II, III, V, and VI

Answers were Sorted based on User's Feedback



Software Quality Assurance Progress: Scenario I. Defining SQA milestones II. Assi..

Answer / madhu kiran

choice 1

Is This Answer Correct ?    0 Yes 0 No

Software Quality Assurance Progress: Scenario I. Defining SQA milestones II. Assi..

Answer / livon

Choice 1
I, III, V, and VI

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More QA Concepts Interview Questions

What is Database Testing? How will you do it?

10 Answers  


What should QA require of Development?

0 Answers   Value Labs,


In which of the software testing phase is QA involved & QC not involved?

2 Answers   Uniken,


What is the risk factor problem related to project? risk factor ratio in the project?

0 Answers  


What type of documents would you need for QA/QC/Testing?

4 Answers  






What documents QA team needs from Development to orginize a QA process

4 Answers  


What kind of things that forbidden to do by a SQA Tester if He/ She don’t want to get fired?

0 Answers  


Formal Testing?

2 Answers  


what all we should write to prepare a test report?plz wit template?

1 Answers  


how do i know that I am using 32 bit Windows

5 Answers   SunGard,


What is difference between retesting and regression testing?

0 Answers  


How many levels of ISTQB Certifications r there? What r they? When they will be commenced?

2 Answers  


Categories