Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


now a shunt motor is practically a constant speed motor ,
then how does it meet the increase or decrease in the load ?



now a shunt motor is practically a constant speed motor , then how does it meet the increase or de..

Answer / rakesh

now when load torque increase then to remain in the steady
state i.e to make the developed torque equal to load torque
the corresponding armature current increasee ( t@i) so the
increased mechanical power comes frm the increased armature
current

Is This Answer Correct ?    4 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

Explain dc generator with its types?

0 Answers  


how to calaculate the amps in transformer ?

2 Answers  


Can we step up a 230V supply to 400V using a single phase transformer??

2 Answers  


How to Calculate Transformer Earthing Electrode Rod Size both Body and neutral Earthing ? Any Standard Formula? Please Suggted

0 Answers   EnPro,


How you calculate the repturing capacity of a HRC fuse

0 Answers   CPCL, RSCL,


where can the transformer having vector group Yny0 be used??

0 Answers   GK Power, NEA, Petrotech,


If DG runing time Neutral earth connection Dissconect what will be the effect in load and equipments.

3 Answers   GE, HP, Reliance,


How should i design a 1ph & 3 ph transformer. Kindly let meknow all steps and formulaes related to design from scratch.

0 Answers  


What is d diff. btw Online & Offline UPS???

4 Answers   Emerson,


our factory is going under construction mean time transformer 1000 kva 2 nos &load break swithch 12 kv & 4 nos 750 kva 2 nos & 380 kva 2 nos generator to be errcted.how to arrange earth pits &how to earth connect & neutral pit how to calculate in earth bit size.

0 Answers  


Where there is voltage,there must be current.Is this right or wrong??

10 Answers  


lead acid battery electrolity?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)